2467 S BUTLER AVE 90064

Certificate Information: 2467 S BUTLER AVE 90064

Application / Permit
21014-20000-00688
Plan Check / Job No.
B21VN01801
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 10'-4" X 15'-10" MASTER BEDROOM AND REMODEL THROUGHOUT (E) 1-STORY SFD
Permit Issued
Issued on 10/22/2021
Issuing Office
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 JENNIFER LEE
Corrections Issued 3/9/2021 JENNIFER LEE
Applicant returned to address corrections 7/26/2021 JENNIFER LEE
Applicant returned to address corrections 9/28/2021 JENNIFER LEE
Plan Check Approved 10/18/2021 JENNIFER LEE
Building Plans Picked Up 10/19/2021 APPLICANT
Issued 10/22/2021 APPLICANT
CofO in Progress 11/21/2022 ASHLEY THOMPSON
Permit Finaled 11/30/2022 DANIEL ORRANTE
CofO Issued 11/30/2022 DANIEL ORRANTE
Permit Finaled 11/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/6/2021 ANTHONY MAINEZ
Sewer availability Cleared 4/6/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 4/12/2021 ANTHONY MAINEZ
Specific Plan Cleared 5/4/2021 MIGUEL GAMBOA
Specific Plan Cleared 6/3/2021 VALERIA CEJA

Contact Information

Contractor Zaven Construction Inc; Lic. No.: 1078839-B 943 CAMBRIDGE DRIVE      BURBANK, CA 91504

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/17/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 12/17/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/20/2021 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 12/29/2021 Not Ready for Inspection JOHNNY MIRANDA
Underground Mechanical 2/16/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/1/2022 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Approval EVAN COOPER
Pre-Inspection 3/1/2022 Not Ready for Inspection EVAN COOPER
Underground Mechanical 3/1/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 3/11/2022 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 3/11/2022 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 3/11/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/15/2022 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 3/15/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/17/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 3/17/2022 Approved OGANES TARAKHCHYAN
MERV13>=Rough 3/17/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/17/2022 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 3/17/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/20/2022 Partial Approval JUAN VALENZUELA
Pre-Inspection 4/22/2022 Partial Approval JOHNNY MIRANDA
Insulation 4/26/2022 Approved CLAYTON GRAHAM
Drywall Nailing 5/6/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/12/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/18/2022 Approved KENNETH NAGLE
Pre-Inspection 6/10/2022 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Final 6/17/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 6/24/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/24/2022 Approved OGANES TARAKHCHYAN
Green Building Final 6/24/2022 Approved OGANES TARAKHCHYAN
MERV13>=Final 6/24/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 7/1/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 7/1/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 7/1/2022 Approved OGANES TARAKHCHYAN
Pre-Inspection 7/1/2022 Approved OGANES TARAKHCHYAN
Service/Power Release 7/7/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 8/1/2022 Approved JOHN KIDWELL
Final 11/21/2022 Conditional Approval ASHLEY THOMPSON