2676 E LOOSMORE ST 90065

Certificate Information: 2676 E LOOSMORE ST 90065

Application / Permit
21014-20000-00683
Plan Check / Job No.
B21VN01785
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
8' 9" X 11'11"ADDITION OF A MASTER BEDROOM, INTERIOR REMODEL AND NEW SPLIT A/C SYSTEM WITH RE-WIRE.
Permit Issued
Issued on 4/26/2021
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/2/2021 PINANK PATEL
Corrections Issued 3/3/2021 PINANK PATEL
Applicant returned to address corrections 3/25/2021 PINANK PATEL
Building Plans Picked Up 3/31/2021 APPLICANT
Plan Check Approved 4/26/2021 PINANK PATEL
Issued 4/26/2021 APPLICANT
CofO in Progress 5/1/2024 CHARLES BOGHOSKHAN
CofO Issued 5/1/2024 DEROLD HAUFF
Permit Finaled 5/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/2/2021 PINANK PATEL
Eng Process Fee Ord 176,300 Cleared 3/5/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 3/5/2021 RENZ SORIANO
Supp. Use District POD/CDO/TDO Cleared 4/6/2021 ADRINEH MELKONIAN
ZI Cleared 4/6/2021 ADRINEH MELKONIAN

Contact Information

Contractor Evolution Design & Development Inc; Lic. No.: 999377-B 14545 VICTORY BLVD SUITE 407      VAN NUYS, CA 91411

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/5/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/5/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/7/2021 Approved OSVALDO PARAMO
Wood Frame 5/18/2021 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 5/27/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 5/27/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 6/3/2021 Approved OSVALDO PARAMO
Wood Frame 6/10/2021 Approved OSVALDO PARAMO
Drywall Nailing 6/28/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/28/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 6/28/2021 Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 12/13/2021 Order to Comply Issued OSVALDO PARAMO
BUILDING-Rough-Frame 7/5/2022 Approved OSVALDO PARAMO
Final 7/5/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 7/5/2022 Approved OSVALDO PARAMO
Green Building Rough 7/5/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 7/5/2022 Approved OSVALDO PARAMO
Final 3/29/2023 Not Ready for Inspection OSVALDO PARAMO
Final 4/26/2024 OK to Issue CofO OSVALDO PARAMO