2676 E LOOSMORE ST 90065
Certificate Information: 2676 E LOOSMORE ST 90065
- Application / Permit
- 21014-20000-00683
- Plan Check / Job No.
- B21VN01785
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8' 9" X 11'11"ADDITION OF A MASTER BEDROOM, INTERIOR REMODEL AND NEW SPLIT A/C SYSTEM WITH RE-WIRE.
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2021 | PINANK PATEL |
| Corrections Issued | 3/3/2021 | PINANK PATEL |
| Applicant returned to address corrections | 3/25/2021 | PINANK PATEL |
| Building Plans Picked Up | 3/31/2021 | APPLICANT |
| Plan Check Approved | 4/26/2021 | PINANK PATEL |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 5/1/2024 | CHARLES BOGHOSKHAN |
| CofO Issued | 5/1/2024 | DEROLD HAUFF |
| Permit Finaled | 5/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/2/2021 | PINANK PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | RENZ SORIANO |
| Supp. Use District POD/CDO/TDO | Cleared | 4/6/2021 | ADRINEH MELKONIAN |
| ZI | Cleared | 4/6/2021 | ADRINEH MELKONIAN |
Contact Information
| Contractor | Evolution Design & Development Inc; Lic. No.: 999377-B | 14545 VICTORY BLVD SUITE 407 VAN NUYS, CA 91411 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/5/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/5/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/7/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/18/2021 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/27/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 5/27/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/3/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 6/10/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/28/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/28/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/28/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 12/13/2021 | Order to Comply Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/5/2022 | Approved | OSVALDO PARAMO |
| Final | 7/5/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 7/5/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 7/5/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/5/2022 | Approved | OSVALDO PARAMO |
| Final | 3/29/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 4/26/2024 | OK to Issue CofO | OSVALDO PARAMO |