10427 W RAINIER ST 91352

Certificate Information: 10427 W RAINIER ST 91352

Application / Permit
21014-20000-00653
Plan Check / Job No.
B21VN01731
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
32'-1" X 16'-5" IRREG SHAPED ADDITION TO ENLARGE (E) BEDROOM AND ADD NEW BEDROOM AND CLOSET. 20'-3" X 5'-5" PATIO COVER ADDITION. ALL WORK PER ENGINEER
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/26/2021 JEROME MAGAT PALMA
Corrections Issued 3/1/2021 JEROME MAGAT PALMA
Plan Check Approved 7/29/2021 JEROME MAGAT PALMA
Building Plans Picked Up 9/17/2021 APPLICANT
Issued 9/23/2021 APPLICANT
CofO in Progress 6/2/2023 DAVID ANDERSON
Permit Finaled 6/7/2023 MICHAEL SMITH
CofO Issued 6/7/2023 MICHAEL SMITH
Permit Finaled 6/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2021 LEE GUILBEAUX
Sewer availability Cleared 3/10/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/11/2021 LEE GUILBEAUX

Contact Information

Contractor D P Construction; Lic. No.: 867245-B 4443 W 164TH ST      LAWNDALE, CA 90260
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/16/2021 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 1/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 1/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Rough 1/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/15/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/15/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 2/15/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 2/15/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/15/2022 Conditional Approval CHRISTOPHER DELLEFIELD
MERV13>=Rough 2/15/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 2/22/2022 Approved WILLIAM WREN
Insulation 2/22/2022 Approved WILLIAM WREN
ELECTRICAL-Final 4/22/2022 Approved MICHEL ABAJAN
Final 4/22/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 4/22/2022 Approved MICHEL ABAJAN
HVAC-Final 4/22/2022 Approved MICHEL ABAJAN
MERV13>=Final 4/22/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 4/22/2022 Approved MICHEL ABAJAN
Final 6/2/2023 OK to Issue CofO DAVID ANDERSON