13648-13650 N GARRICK AVE 91342
Certificate Information: 13648-13650 N GARRICK AVE 91342
- Application / Permit
- 21014-20000-00648
- Plan Check / Job No.
- B21VN01713
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC***CONVERT AND ADDITION TO EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SHAHEN AKELYAN |
| Corrections Issued | 3/4/2021 | SHAHEN AKELYAN |
| Applicant returned to address corrections | 4/13/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/28/2021 | LUISANGEL VALENZUELA |
| Issued | 7/6/2021 | APPLICANT |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| CofO in Progress | 9/16/2022 | ARAM AVEDISIAN |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/8/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/9/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 3/10/2021 | BRIAN MILLER |
| Construction near power lines | Cleared | 6/12/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2021 | ADRIAN CASTRO |
| Construction within easement | Cleared | 6/18/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Bellagio Design Build Corporation; Lic. No.: 935571-B | 19336 CALVERT STREET TARZANA, CA 91335 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2021 | Partial Approval | JEFFREY PARD |
| Sewer | 7/26/2021 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 7/26/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 10/6/2021 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 10/12/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 11/1/2021 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 11/9/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 11/10/2021 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 11/15/2021 | Conditional Approval | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 11/17/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 12/7/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/6/2022 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/6/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/13/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 1/13/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/13/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 1/19/2022 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 1/20/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/20/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 1/20/2022 | Approved | JOHN HAYES |
| Sewer | 1/20/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 2/1/2022 | Approved | JOHN HAYES |
| Green Building Rough | 2/1/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 2/1/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/1/2022 | Partial Approval | JOHN HAYES |
| Wood Frame | 2/1/2022 | Approved | JOHN HAYES |
| Insulation | 2/10/2022 | Approved | JOHN HAYES |
| Shower Pan | 2/10/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | JOHN HAYES |
| Insulation | 2/22/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/22/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 3/2/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/2/2022 | Approved | JOHN HAYES |
| Special/Order Compliance | 4/5/2022 | Approved | JOHN HAYES |
| Final | 5/12/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 5/12/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/18/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/18/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 5/18/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/18/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/14/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/14/2022 | Approved | ARAM AVEDISIAN |
| Green Building Final | 9/14/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/14/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/16/2022 | OK to Issue CofO | ARAM AVEDISIAN |