1625 S ORANGE GROVE AVE 90019
Certificate Information: 1625 S ORANGE GROVE AVE 90019
- Application / Permit
- 21014-20000-00645
- Plan Check / Job No.
- B21VN01708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. GARAGE AND RECREATION ROOM TO ACCESSORY DWELLING UNIT AND ADD 25'10" x 6' AND 10' x 20' TRELLIS PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENG.
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | JEFFREY TANGONAN |
| Corrections Issued | 3/6/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 6/10/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 7/16/2021 | JEFFREY TANGONAN |
| Issued | 7/26/2022 | APPLICANT |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| CofO in Progress | 8/22/2023 | JOSE AVILA |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/18/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/25/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 5/28/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | O'Brien,, Kathleen Anne; Lic. No.: C49498 | 1058 PACIFIC AVE SIMI VALLEY, CA 93065 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2022 | Conditional Approval | JOSE AVILA |
| Sewer | 9/29/2022 | Partial Approval | JOSE AVILA |
| METHANE-Rough | 10/13/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 10/19/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 11/22/2022 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 11/22/2022 | Approved | MICHAEL LEWIS |
| Sewer | 11/22/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/22/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 2/22/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 3/6/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 3/6/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/6/2023 | Approved | JOSE AVILA |
| Wood Frame | 3/31/2023 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 4/5/2023 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | JOSE AVILA |
| Insulation | 5/16/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/16/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 6/1/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 6/1/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/18/2023 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 7/18/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 7/18/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 7/18/2023 | Approved | JOSE AVILA |
| Final | 8/1/2023 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 8/1/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Approved | JOSE AVILA |
| Final | 8/8/2023 | Corrections Issued | JOSE AVILA |
| Final | 8/22/2023 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 8/22/2023 | Approved | JOSE AVILA |