11114 W ARCHWOOD ST 91606

Certificate Information: 11114 W ARCHWOOD ST 91606

Application / Permit
21014-20000-00640
Plan Check / Job No.
B21VN01701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 5'-0" x 20'-0" TO AND CONVERT (E) 20'-0" x 20'-0" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 5/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Corrections Issued 3/6/2021 SARKIS HARABEDIAN
Assigned to Plan Check Engineer 3/8/2021 SARKIS HARABEDIAN
Corrections Issued 4/29/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 6/16/2021 SARKIS HARABEDIAN
Building Plans Picked Up 6/25/2021 APPLICANT
Applicant returned to address corrections 9/16/2022 ADAM HEGAZI
Plan Check Approved 11/18/2022 SAMUEL GONZALEZ
Plan Check Approved 4/7/2023 CRISTINA SALAZAR
Issued 5/5/2023 APPLICANT
CofO in Progress 4/10/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/30/2026 RUBEN SALAS
CofO Issued 4/30/2026 RUBEN SALAS
Permit Finaled 4/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/17/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/1/2022 CARLOS AGUILERA
Sewer availability Cleared 6/1/2022 CARLOS AGUILERA
Construction near power lines Cleared 10/22/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Yassin,, Diaa Aldin; Lic. No.: C56295 2207 MERCED AVE      SOUTH EL MONTE, CA 91733

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/23/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/20/2023 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 7/7/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/15/2023 No Access for Inspection JOHN HAYES
Footing/Foundation/Slab 9/19/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 11/15/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 11/15/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/5/2023 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 4/22/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/22/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 4/22/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/10/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/10/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/10/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/10/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 5/24/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/24/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/15/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/5/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 9/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 9/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 10/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 10/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/14/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 2/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 2/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 2/10/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 2/10/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/17/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 2/17/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 2/17/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/20/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/20/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Service/Power Release 3/20/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Final 4/3/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 4/3/2026 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/3/2026 Approved ROBERTO PALACIOS-LOPEZ