4429 N GENTRY AVE 91607

Certificate Information: 4429 N GENTRY AVE 91607

Application / Permit
21014-20000-00632
Plan Check / Job No.
B21VN01683
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF 21'-4" X 33'-2" IRREGULAR SHAPE AND 10' X 3'-6" (N) ATTACHED PORCH TO AND CONVERT THE 20'-3" X 25'-2" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEER.
Permit Issued
Issued on 7/13/2021
Issuing Office
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 PARISA ZAHABI
Corrections Issued 3/4/2021 PARISA ZAHABI
Plan Check Approved 7/1/2021 PARISA ZAHABI
Building Plans Picked Up 7/1/2021 APPLICANT
Issued 7/13/2021 APPLICANT
CofO in Progress 3/1/2023 JACK KARGODORIAN
CofO Issued 3/13/2023 DANIEL ORRANTE
Permit Finaled 3/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/11/2021 GUILLERMO PETRA
CPC Cleared 3/11/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 3/11/2021 GUILLERMO PETRA
Sewer availability Cleared 3/11/2021 GUILLERMO PETRA
ZI Cleared 3/11/2021 LAUREN PADICK
Construction near power lines Cleared 4/22/2021 RIDWAN HARDY
Construction within easement Cleared 4/22/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/18/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/21/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 6541 ODESSA AVE UNIT 11      LAKE BALBOA, CA 91406

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/8/2021 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 10/14/2021 Approved MICHAEL PELHAM
Footing/Foundation/Slab 10/15/2021 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 12/7/2021 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 12/7/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/8/2021 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 12/8/2021 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Partial Approval DAVID MATSON
Green Building Rough 12/8/2021 Approved DAVID MATSON
HVAC-Rough 12/8/2021 Corrections Issued DAVID MATSON
PLUMBING-Rough 12/8/2021 Corrections Issued DAVID MATSON
Underground Mechanical 12/20/2021 Partial Approval THOMAS FINNILA
Sewer 1/6/2022 Approved CALEB MEISTER
Underground Mechanical 1/6/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 3/30/2022 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 3/30/2022 Corrections Issued DAVID MATSON
HVAC-Rough 3/30/2022 Corrections Issued DAVID MATSON
PLUMBING-Rough 3/30/2022 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 4/11/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 4/11/2022 Approved THOMAS FINNILA
HVAC-Rough 4/11/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/21/2022 Corrections Issued ARAM AVEDISIAN
Interior/Exterior Lathing 4/21/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 5/4/2022 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 5/4/2022 Approved THOMAS FINNILA
Shower Pan 5/4/2022 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 5/6/2022 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 5/6/2022 Conditional Approval DAVID MATSON
HVAC-Rough 5/11/2022 Approved JUSTIN HAWLEY
Insulation 5/11/2022 Approved JUSTIN HAWLEY
Shower Pan 5/11/2022 Approved JUSTIN HAWLEY
Drywall Nailing 5/26/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/7/2022 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/15/2022 Approved JOHN COLEMAN
Final 12/15/2022 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 12/15/2022 Approved JOHN COLEMAN
Green Building Final 12/15/2022 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Approved JOHN COLEMAN
Smoke Detectors 12/15/2022 Approved JOHN COLEMAN
Final 2/16/2023 No Access for Inspection JACK KARGODORIAN
Green Building Final 2/16/2023 No Access for Inspection JACK KARGODORIAN
Final 2/23/2023 Not Ready for Inspection JACK KARGODORIAN
Green Building Final 2/23/2023 Approved JACK KARGODORIAN
Final 2/28/2023 OK to Issue CofO JACK KARGODORIAN