9037 N WOODLEY AVE 91343

Certificate Information: 9037 N WOODLEY AVE 91343

Application / Permit
21014-20000-00625
Plan Check / Job No.
B21VN01665
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
35'-10" X 43'-0" IRREG SHAPED ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE PER LAMC 12.22 A. 33(c) and (d)
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 JEROME MAGAT PALMA
Corrections Issued 3/6/2021 JEROME MAGAT PALMA
Plan Check Approved 8/13/2021 JEROME MAGAT PALMA
Building Plans Picked Up 8/19/2021 APPLICANT
Issued 12/9/2021 APPLICANT
CofO in Progress 8/26/2022 RAUL OLAGI
Permit Finaled 9/3/2022 DEROLD HAUFF
CofO Issued 9/3/2022 DEROLD HAUFF
Permit Finaled 9/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/10/2021 GUILLERMO PETRA
Sewer availability Cleared 3/11/2021 GUILLERMO PETRA
Low Impact Development Cleared 7/13/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/14/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/9/2021 CARLOS AGUILERA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Artisan Build Group; Lic. No.: 1059364-B 15210 VENTURA BLVD #310      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 2/22/2022 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/10/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/14/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Corrections Issued RAUL OLAGI
Sewer 4/22/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/12/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/12/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Approved RAUL OLAGI
Green Building Rough 5/12/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 5/12/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/12/2022 Approved RAUL OLAGI
Underground Mechanical 5/12/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 6/3/2022 Approved JAVIER RAMOS JR
HVAC-Rough 6/3/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/16/2022 Approved ALAN MORELOS
Green Building Rough 6/16/2022 Not Ready for Inspection ALAN MORELOS
Wood Frame 6/16/2022 Approved ALAN MORELOS
Deputy Drilled-In Anchors 6/21/2022 Approved ALAN MORELOS
Green Building Rough 6/23/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 6/23/2022 Approved DEANDRE HOFFMAN
Shower Pan 6/23/2022 Approved DEANDRE HOFFMAN
Insulation 6/29/2022 Approved ALAN MORELOS
Drywall Nailing 7/6/2022 Approved CALEB MEISTER
ELECTRICAL-Final 8/12/2022 Corrections Issued RAUL OLAGI
Final 8/12/2022 Corrections Issued RAUL OLAGI
Green Building Final 8/12/2022 Approved RAUL OLAGI
HVAC-Final 8/12/2022 Approved RAUL OLAGI
PLUMBING-Final 8/12/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/12/2022 Approved RAUL OLAGI
ELECTRICAL-Final 8/26/2022 Approved RAUL OLAGI
Final 8/26/2022 OK to Issue CofO RAUL OLAGI