10235 N TINKER AVE 91042

Certificate Information: 10235 N TINKER AVE 91042

Application / Permit
21014-20000-00621
Plan Check / Job No.
B21VN01656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 18'-6" X 26'-1" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/3/2021 RAPHAEL ROSAS
Corrections Issued 3/3/2021 RAPHAEL ROSAS
Building Plans Picked Up 3/5/2021 APPLICANT
Applicant returned to address corrections 3/26/2021 RAPHAEL ROSAS
Plan Check Approved 4/1/2021 RAPHAEL ROSAS
Issued 4/20/2021 APPLICANT
CofO in Progress 9/8/2021 DAVID MATSON
CofO Issued 9/16/2021 MICHAEL SMITH
Permit Finaled 9/16/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/8/2021 GABRIEL ROBLES
Sewer availability Cleared 3/8/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 3/10/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 4/1/2021 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/4/2021 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 5/6/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/21/2021 Partial Approval MATTHEW NELSON
PLUMBING-Rough 5/21/2021 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Approved GREGG CUMMINGS
Green Building Rough 6/21/2021 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/24/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 6/24/2021 Approved MATTHEW NELSON
Green Building Rough 6/24/2021 Approved MATTHEW NELSON
HVAC-Rough 6/24/2021 Approved MATTHEW NELSON
PLUMBING-Rough 6/24/2021 Approved MATTHEW NELSON
Insulation 7/1/2021 Corrections Issued DEANDRE HOFFMAN
Interior/Exterior Lathing 7/1/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 7/8/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 7/8/2021 Approved DEANDRE HOFFMAN
Shower Pan 7/8/2021 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Final 7/12/2021 Corrections Issued DAVID MATSON
Shower Pan 7/12/2021 Partial Approval DAVID MATSON
ELECTRICAL-Final 8/11/2021 Approved WILLIAM KUEHN
Final 8/11/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 8/11/2021 Approved WILLIAM KUEHN
HVAC-Final 8/11/2021 Approved WILLIAM KUEHN
PLUMBING-Final 8/11/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 8/11/2021 Approved WILLIAM KUEHN
Final 8/18/2021 Corrections Issued WILLIAM KUEHN
Final 8/19/2021 Corrections Issued WILLIAM KUEHN
Final 9/8/2021 OK to Issue CofO DAVID MATSON