4100 N BAKMAN AVE 91602

Certificate Information: 4100 N BAKMAN AVE 91602

Application / Permit
21014-20000-00620
Plan Check / Job No.
B21VN01652
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF GUEST BEDROOM AT FRONT, FAMILY ROOM AT REAR ON 1ST FLOOR, CLOSET & DECK ON 2ND FLOOR & COVERED PATIO AT FRONT TO (E) 2-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 NILOOFAR MEHRAIN
Corrections Issued 2/23/2021 NILOOFAR MEHRAIN
Quality Review Completed 2/23/2021 CHON CHIO KUO
Building Plans Picked Up 2/23/2021 APPLICANT
Applicant returned to address corrections 3/18/2021 NILOOFAR MEHRAIN
Plan Check Approved 3/23/2021 NILOOFAR MEHRAIN
Issued 4/13/2021 APPLICANT
CofO in Progress 2/24/2023 JACK KARGODORIAN
Permit Finaled 4/11/2023 MICHAEL SMITH
CofO Issued 4/11/2023 MICHAEL SMITH
Permit Finaled 4/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 3/4/2021 GABRIEL ROBLES
Sewer availability Cleared 3/4/2021 GABRIEL ROBLES
ZI Cleared 3/15/2021 DANG NGUYEN

Contact Information

Contractor D L Williams Construction; Lic. No.: 703664-B 13071 HOMWOOD CT      VICTORVILLE, CA 92392
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/7/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 5/14/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/21/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 9/21/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 9/21/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/21/2021 Approved THOMAS FINNILA
PLUMBING-Rough 9/21/2021 Approved THOMAS FINNILA
Insulation 9/30/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/1/2021 Approved THOMAS FINNILA
Green Building Rough 10/1/2021 Approved THOMAS FINNILA
Insulation 10/4/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 10/12/2021 Approved CALEB MEISTER
Final 1/21/2022 OK to Issue CofO MATT KELLERMAN
Green Building Final 1/21/2022 Approved MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 1/21/2022 Approved MATT KELLERMAN