4100 N BAKMAN AVE 91602
Certificate Information: 4100 N BAKMAN AVE 91602
- Application / Permit
- 21014-20000-00620
- Plan Check / Job No.
- B21VN01652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF GUEST BEDROOM AT FRONT, FAMILY ROOM AT REAR ON 1ST FLOOR, CLOSET & DECK ON 2ND FLOOR & COVERED PATIO AT FRONT TO (E) 2-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/23/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/23/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Applicant returned to address corrections | 3/18/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/23/2021 | NILOOFAR MEHRAIN |
| Issued | 4/13/2021 | APPLICANT |
| CofO in Progress | 2/24/2023 | JACK KARGODORIAN |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/4/2021 | GABRIEL ROBLES |
| ZI | Cleared | 3/15/2021 | DANG NGUYEN |
Contact Information
| Contractor | D L Williams Construction; Lic. No.: 703664-B | 13071 HOMWOOD CT VICTORVILLE, CA 92392 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2021 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 5/14/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/21/2021 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/21/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/21/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/21/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 9/21/2021 | Approved | THOMAS FINNILA |
| Insulation | 9/30/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/1/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/1/2021 | Approved | THOMAS FINNILA |
| Insulation | 10/4/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 10/12/2021 | Approved | CALEB MEISTER |
| Final | 1/21/2022 | OK to Issue CofO | MATT KELLERMAN |
| Green Building Final | 1/21/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 1/21/2022 | Approved | MATT KELLERMAN |