10839 N HASKELL AVE 91344

Certificate Information: 10839 N HASKELL AVE 91344

Application / Permit
21014-20000-00609
Plan Check / Job No.
B21VN01625
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14' 2" X 16' 5" OFFICE ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 GURUNATH NESARAJAH
Corrections Issued 2/27/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/9/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 5/10/2021 JEROME MAGAT PALMA
Plan Check Approved 6/10/2021 GURUNATH NESARAJAH
Building Plans Picked Up 6/25/2021 APPLICANT
Issued 7/14/2021 APPLICANT
CofO in Progress 2/17/2023 JAVIER RAMOS JR
Permit Finaled 4/26/2023 MICHAEL SMITH
CofO Issued 4/26/2023 MICHAEL SMITH
Permit Finaled 4/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/2/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/3/2021 Partial Approval MARK JOHNSON
Deputy Drilled-In Anchors 9/8/2021 Conditional Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/1/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/1/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/18/2022 Approved JAVIER RAMOS JR
Green Building Rough 4/18/2022 Approved JAVIER RAMOS JR
Insulation 4/18/2022 Approved JAVIER RAMOS JR
MERV13>=Rough 4/18/2022 Approved JAVIER RAMOS JR
Drywall Nailing 5/6/2022 Approved JAVIER RAMOS JR
Final 5/6/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 5/6/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 5/6/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Final 5/6/2022 Not Ready for Inspection JAVIER RAMOS JR
Masonry Wall/Backfill 5/6/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 5/6/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 9/16/2022 No Access for Inspection DEANDRE HOFFMAN
PLUMBING-Rough 9/16/2022 Not Ready for Inspection DEANDRE HOFFMAN
Final 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Final 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 2/16/2023 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 2/16/2023 Approved JAVIER RAMOS JR
Green Building Final 2/16/2023 Approved JAVIER RAMOS JR
MERV13>=Final 2/16/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/16/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 2/16/2023 Approved JAVIER RAMOS JR