9315 N WHITE OAK AVE 91325

Certificate Information: 9315 N WHITE OAK AVE 91325

Application / Permit
21014-20000-00602
Plan Check / Job No.
B21VN01620
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING. NEW ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 6/23/2021
Issuing Office
Current Status
CofO Issued on 5/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 ALYSSA N NARCISO
Corrections Issued 2/24/2021 ALYSSA N NARCISO
Quality Review Completed 2/26/2021 STEVEN KIM
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 6/22/2021 ALYSSA N NARCISO
Plan Check Approved 6/23/2021 ALYSSA N NARCISO
Issued 6/23/2021 APPLICANT
CofO in Progress 5/4/2023 JAVIER RAMOS JR
Permit Finaled 5/17/2023 MICHAEL SMITH
CofO Issued 5/17/2023 MICHAEL SMITH
Permit Finaled 5/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 2/26/2021 ADRIAN CASTRO
Sewer availability Cleared 2/26/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/2/2021 ADRIAN CASTRO
Trees in Parkway Cleared 4/20/2021 JOHN KIM
Hydrant and Access approval Cleared 4/23/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/12/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/15/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Mkrtchyan,, Gor; Lic. No.: L7387 16730 CANTLAY ST      VAN NUYS, CA 91406

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/25/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 6/30/2021 Approved MARK JOHNSON
Deputy Reinf. Concrete 7/2/2021 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 7/19/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 7/26/2021 Partial Approval MARK JOHNSON
Green Building Rough 7/26/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 8/20/2021 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Approved MARK JOHNSON
Deputy Wood Construction 9/17/2021 No Access for Inspection MARK JOHNSON
BUILDING-Rough-Frame 11/8/2021 Not Ready for Inspection PETER FOLLING
Drywall Nailing 11/8/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 11/8/2021 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved PETER FOLLING
Green Building Rough 11/8/2021 Not Ready for Inspection PETER FOLLING
HVAC-Rough 11/8/2021 Approved PETER FOLLING
PLUMBING-Rough 11/8/2021 Not Ready for Inspection PETER FOLLING
Wood Frame 11/8/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 11/10/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/16/2021 Approved MARK JOHNSON
Green Building Rough 11/16/2021 Approved MARK JOHNSON
Insulation 11/23/2021 Approved MARK JOHNSON
Drywall Nailing 12/1/2021 Approved ROBERT GOLD
Interior/Exterior Lathing 12/1/2021 Approved ROBERT GOLD
Shower Pan 12/1/2021 Approved ROBERT GOLD
HVAC-Final 1/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 4/13/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/13/2023 Approved JAVIER RAMOS JR
HVAC-Final 4/13/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 4/13/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/13/2023 Approved JAVIER RAMOS JR
Final 5/3/2023 OK to Issue CofO JAVIER RAMOS JR