9315 N WHITE OAK AVE 91325
Certificate Information: 9315 N WHITE OAK AVE 91325
- Application / Permit
- 21014-20000-00602
- Plan Check / Job No.
- B21VN01620
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING. NEW ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 6/23/2021
- Issuing Office
- Current Status
- CofO Issued on 5/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | ALYSSA N NARCISO |
| Corrections Issued | 2/24/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 2/26/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| Applicant returned to address corrections | 6/22/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 6/23/2021 | ALYSSA N NARCISO |
| Issued | 6/23/2021 | APPLICANT |
| CofO in Progress | 5/4/2023 | JAVIER RAMOS JR |
| Permit Finaled | 5/17/2023 | MICHAEL SMITH |
| CofO Issued | 5/17/2023 | MICHAEL SMITH |
| Permit Finaled | 5/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 2/26/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/26/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 4/20/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/23/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/12/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Mkrtchyan,, Gor; Lic. No.: L7387 | 16730 CANTLAY ST VAN NUYS, CA 91406 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/25/2021 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 6/30/2021 | Approved | MARK JOHNSON |
| Deputy Reinf. Concrete | 7/2/2021 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/19/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/26/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 7/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/20/2021 | Corrections Issued | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Approved | MARK JOHNSON |
| Deputy Wood Construction | 9/17/2021 | No Access for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 11/8/2021 | Not Ready for Inspection | PETER FOLLING |
| Drywall Nailing | 11/8/2021 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 11/8/2021 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | PETER FOLLING |
| Green Building Rough | 11/8/2021 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 11/8/2021 | Approved | PETER FOLLING |
| PLUMBING-Rough | 11/8/2021 | Not Ready for Inspection | PETER FOLLING |
| Wood Frame | 11/8/2021 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 11/10/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 11/16/2021 | Approved | MARK JOHNSON |
| Insulation | 11/23/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 12/1/2021 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 12/1/2021 | Approved | ROBERT GOLD |
| Shower Pan | 12/1/2021 | Approved | ROBERT GOLD |
| HVAC-Final | 1/5/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/13/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/13/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/13/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/13/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/13/2023 | Approved | JAVIER RAMOS JR |
| Final | 5/3/2023 | OK to Issue CofO | JAVIER RAMOS JR |