6608 W DREXEL AVE 90048

Certificate Information: 6608 W DREXEL AVE 90048

Application / Permit
21014-20000-00584
Plan Check / Job No.
B21VN01584
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-0" x 30'-4" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED STORAGE.
Permit Issued
Issued on 3/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/26/2021 JEROME MAGAT PALMA
Corrections Issued 2/27/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 5/12/2021 SARKIS HARABEDIAN
Building Plans Picked Up 5/14/2021 APPLICANT
Applicant returned to address corrections 6/7/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 1/24/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 11/14/2022 MOHAMMAD ESMAILI
Plan Check Approved 3/20/2023 SARKIS HARABEDIAN
Issued 3/20/2023 APPLICANT
CofO in Progress 3/29/2024 MEL KHACHATOURIAN
Permit Finaled 4/9/2024 DANIEL ORRANTE
CofO Issued 4/9/2024 DANIEL ORRANTE
Permit Finaled 4/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/5/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 3/5/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 3/8/2021 RENZ SORIANO
Sewer availability Cleared 3/8/2021 RENZ SORIANO
CPC Cleared 3/9/2021 RUBEN VASQUEZ
ZI Cleared 4/27/2021 RUBEN VASQUEZ
Construction near power lines Cleared 5/3/2021 RIDWAN HARDY
Construction within easement Cleared 5/3/2021 RIDWAN HARDY
Low Impact Development Cleared 9/21/2022 ROGELIO CORTES
Construction near power lines Cleared 10/3/2022 OSCAR CASTRO
Construction within easement Cleared 10/3/2022 OSCAR CASTRO

Contact Information

Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303
Engineer Sin,, John P; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/2/2023 Partial Inspection JEREMY TODD
Footing/Foundation/Slab 5/19/2023 Approved JEREMY TODD
METHANE-Barrier 5/19/2023 Approved JEREMY TODD
METHANE-Subgrade 5/19/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval JEREMY TODD
Underground Mechanical 6/7/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Approval JEREMY TODD
PLUMBING-Rough 7/14/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 7/31/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval ARAM AVEDISIAN
HVAC-Rough 7/31/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/23/2023 Approved MEL KHACHATOURIAN
Green Building Rough 8/23/2023 Approved MEL KHACHATOURIAN
METHANE-Rough 8/23/2023 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 8/23/2023 Approved MEL KHACHATOURIAN
Shower Pan 8/29/2023 Approved MEL KHACHATOURIAN
Insulation 8/30/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/30/2023 Partial Approval MEL KHACHATOURIAN
Insulation 9/1/2023 Conditional Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 9/1/2023 Approved MEL KHACHATOURIAN
Drywall Nailing 9/11/2023 Conditional Approval MEL KHACHATOURIAN
Final 2/13/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Final 2/13/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 2/13/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 2/13/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 3/11/2024 Partial Approval MEL KHACHATOURIAN
Final 3/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Final 3/11/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 3/11/2024 Corrections Issued MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 3/11/2024 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 3/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 3/11/2024 Approved MEL KHACHATOURIAN
Final 3/14/2024 OK to Issue CofO MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 3/14/2024 Approved MEL KHACHATOURIAN