600 N SEPULVEDA BLVD 90049
Certificate Information: 600 N SEPULVEDA BLVD 90049
- Application / Permit
- 21014-20000-00581
- Plan Check / Job No.
- B21VN01565
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- REMOVE 36'0" X 24'6" PORTION OF EXISTING 1ST FLOOR OFFICE , NEW 51'4"-1/2" X 18'5-7/16" 1ST FLOOR ADDITION OF A 4 CAR GARAGE AND PATIO TO OFFICE BLDG, NEW 51'4"-1/2" X 18'5-7/16" 2ND FLOOR ADDITION OF OFFICE AREA AND ENCLOSE EXISTING 11'3-15/16" X 18'5-5/8" 1ST FLOOR PATIO TO CONVERT TO THEATHER ROOM AND ENCLOSE 2ND FLOOR PATIO TO RESTROOMS , INTERIOR REMODEL TO (E) OFFICES, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Current Status
- CofO Issued on 4/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 2/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | ALYSSA N NARCISO |
| Green Plans Picked Up | 3/8/2021 | APPLICANT |
| Corrections Issued | 3/12/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 3/16/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/10/2021 | RARES BODEA |
| Applicant returned to address corrections | 5/17/2022 | RARES BODEA |
| Applicant returned to address corrections | 8/9/2022 | RARES BODEA |
| Plan Check Approved | 8/17/2022 | RARES BODEA |
| Issued | 8/18/2022 | APPLICANT |
| TCO Issued (Expire Date: 09-15-2025) | 3/19/2025 | DAVID TSAU |
| CofO in Progress | 4/21/2025 | FARHAD DADBIN |
| Permit Finaled | 4/28/2025 | DAVID TSAU |
| CofO Issued | 4/28/2025 | DAVID TSAU |
| Permit Finaled | 4/28/2025 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 9/1/2021 | MICHAEL AYERS |
| "Q" conditions | Cleared | 11/19/2021 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/3/2021 | ANTHONY MAINEZ |
| Comm Cor/Mini-Mall | Cleared | 2/8/2022 | MAXFIELD VERMY |
| Comm Cor/Mini-Mall | Cleared | 2/14/2022 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 3/9/2022 | JOHN CONNEALLY |
| DAS Clearance | Cleared | 3/22/2022 | ALYSSA N NARCISO |
| Low Impact Development | Cleared | 8/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 8/17/2022 | ALYSSA N NARCISO |
| Grading Pre-Inspection | Cleared | 8/17/2022 | ALYSSA N NARCISO |
Contact Information
| Architect | Goodman,, Benjamin Isaac; Lic. No.: C35193 | 1952 HILLCREST DRIVE LOS ANGELES, CA 90016 |
| Contractor | Machina Group Inc The; Lic. No.: 957436-B | 5758 BURNET AVE VAN NUYS, CA 91411 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/4/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 1/13/2023 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 3/8/2023 | Partial Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 5/24/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 5/26/2023 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/23/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 6/26/2023 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 7/10/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 7/21/2023 | Conditional Approval | PAUL DAVIDSON |
| Reinforced Masonry Frame | 7/24/2023 | Partial Approval | PAUL DAVIDSON |
| Reinforced Masonry Frame | 8/4/2023 | Approved | PAUL DAVIDSON |
| Special/Order Compliance | 8/21/2023 | No Access for Inspection | PAUL DAVIDSON |
| Masonry Wall/Backfill | 8/25/2023 | Partial Inspection | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 9/15/2023 | Conditional Approval | PAUL DAVIDSON |
| Reinforced Masonry Frame | 9/15/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 9/21/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Masonry | 9/29/2023 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 10/17/2023 | Conditional Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Partial Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 10/19/2023 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 10/26/2023 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 12/18/2023 | Conditional Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 12/19/2023 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Approved | PAUL DAVIDSON |
| Deputy Wood Construction | 2/14/2024 | Conditional Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 3/1/2024 | Partial Approval | RICARDO ROBLES |
| Green Building Rough | 3/15/2024 | Approved | PAUL DAVIDSON |
| Insulation | 3/15/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 3/15/2024 | Approved | PAUL DAVIDSON |
| Insulation | 3/18/2024 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 3/29/2024 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 4/9/2024 | Approved | PAUL DAVIDSON |
| Special/Order Compliance | 5/20/2024 | Partial Inspection | PAUL DAVIDSON |
| Grading Pre-Inspection | 7/1/2024 | Partial Inspection | PAUL DAVIDSON |
| Final | 10/10/2024 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 10/10/2024 | Not Ready for Inspection | GRANT WOODS |
| Green Building Final | 10/10/2024 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Not Required | GRANT WOODS |
| Smoke Detectors | 10/10/2024 | Approved | GRANT WOODS |
| Final | 1/7/2025 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 1/7/2025 | Approved | GRANT WOODS |
| Final | 2/6/2025 | Conditional Approval | GRANT WOODS |
| Final | 4/14/2025 | OK to Issue CofO | FARHAD DADBIN |