7553 W VALAHO DR 91042

Certificate Information: 7553 W VALAHO DR 91042

Application / Permit
21014-20000-00580
Plan Check / Job No.
B21VN01563
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
MAJOR REMODEL & ADDITION TO (E) SFD (30'-0"x67'-0") FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 MOHAMMAD ESMAILI
Corrections Issued 3/2/2021 MOHAMMAD ESMAILI
Quality Review Completed 3/15/2021 OMID HEDAYAT
Plan Check Approved 8/10/2021 MOHAMMAD ESMAILI
Issued 8/10/2021 APPLICANT
CofO in Progress 12/12/2022 DAVID ANDERSON
CofO Issued 1/18/2023 MICHAEL SMITH
Permit Finaled 1/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/1/2021 ADRIAN CASTRO
Sewer availability Cleared 4/1/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 4/21/2021 BRIAN MILLER
Hydrant and Access approval Cleared 5/18/2021 MATTHEW CRAIG
Low Impact Development Cleared 7/13/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/16/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/22/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 12/13/2021 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 2/23/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/23/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/9/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 3/15/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 3/15/2022 Approved MATTHEW NELSON
Green Building Rough 3/15/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/15/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 3/15/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/18/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/18/2022 Approved MATTHEW NELSON
Insulation 4/4/2022 Approved WILLIAM WREN
Drywall Nailing 4/25/2022 Approved MATTHEW NELSON
Shower Pan 4/25/2022 Approved MATTHEW NELSON
Underground Mechanical 10/4/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 11/18/2022 Corrections Issued DAVID ANDERSON
Final 11/18/2022 Corrections Issued DAVID ANDERSON
Green Building Final 11/18/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/18/2022 SGSOV Approved DAVID ANDERSON
Smoke Detectors 11/18/2022 Approved DAVID ANDERSON
Final 12/7/2022 Not Ready for Inspection THOMAS FINNILA
Final 12/9/2022 OK to Issue CofO DAVID ANDERSON