24110-24112 W MOBILE ST 91307

Certificate Information: 24110-24112 W MOBILE ST 91307

Application / Permit
21014-20000-00572
Plan Check / Job No.
B21VN01538
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 21'-1" X 22'-0" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A), ADD 13'-0" X 38'-6" FOR NEW MASTER BEDROOM AND EXTEND (E) LIVING ROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/30/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 JENNIFER LEE
Corrections Issued 3/1/2021 JENNIFER LEE
Applicant returned to address corrections 7/20/2021 JENNIFER LEE
Plan Check Approved 8/17/2021 JENNIFER LEE
Issued 8/30/2021 APPLICANT
Building Plans Picked Up 9/1/2021 APPLICANT
CofO in Progress 1/13/2022 TROY SANDERS
Permit Finaled 2/1/2022 MICHAEL SMITH
CofO Issued 2/1/2022 MICHAEL SMITH
Permit Finaled 2/1/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/4/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/5/2021 ADRIAN CASTRO
Sewer availability Cleared 3/5/2021 ADRIAN CASTRO
Low Impact Development Cleared 6/18/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/29/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Shamsrad,, Shima; Lic. No.: C88470 12300 MONTECITO RD 47      SEAL BEACH, CA 90740

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/7/2021 Partial Approval PETER FOLLING
Sewer 9/7/2021 Approved PETER FOLLING
Deputy Drilled-In Anchors 9/10/2021 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 9/10/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/20/2021 Approved TROY SANDERS
ELECTRICAL-Rough 10/20/2021 Approved TROY SANDERS
Green Building Rough 10/20/2021 Not Ready for Inspection TROY SANDERS
HVAC-Rough 10/20/2021 Approved TROY SANDERS
PLUMBING-Rough 10/20/2021 Approved TROY SANDERS
Wood Frame 10/20/2021 Approved TROY SANDERS
HVAC-Rough 11/3/2021 Approved TROY SANDERS
Insulation 11/3/2021 Approved TROY SANDERS
PLUMBING-Rough 11/3/2021 Approved TROY SANDERS
Shower Pan 11/3/2021 Approved TROY SANDERS
Insulation 11/4/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 11/10/2021 Approved TROY SANDERS
Drywall Nailing 11/10/2021 Approved TROY SANDERS
Green Building Rough 11/10/2021 Approved TROY SANDERS
ELECTRICAL-Final 12/8/2021 Approved TROY SANDERS
Final 12/8/2021 Corrections Issued TROY SANDERS
Green Building Final 12/8/2021 Approved TROY SANDERS
HVAC-Final 12/8/2021 Approved TROY SANDERS
PLUMBING-Final 12/8/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Not Ready TROY SANDERS
Smoke Detectors 12/8/2021 Approved TROY SANDERS
Final 1/13/2022 OK to Issue CofO TROY SANDERS
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved TROY SANDERS