6161 N LONGRIDGE AVE 91401

Certificate Information: 6161 N LONGRIDGE AVE 91401

Application / Permit
21014-20000-00565
Plan Check / Job No.
B21VN01522
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12' 8" X 30' 5" ADDITION TO REAR AND REMODEL 19' 4" X 6' 8" PORTION OF (E) SFD TO AD MASTER BATHROOM/CLOSET. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 GURUNATH NESARAJAH
Corrections Issued 2/27/2021 GURUNATH NESARAJAH
Plan Check Approved 4/13/2021 GURUNATH NESARAJAH
Building Plans Picked Up 4/19/2021 APPLICANT
Issued 4/21/2021 APPLICANT
CofO in Progress 9/1/2021 CHRISTOPHE COCHRAN
Permit Finaled 9/16/2021 MICHAEL SMITH
CofO Issued 9/16/2021 MICHAEL SMITH
Permit Finaled 9/16/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/11/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 3/11/2021 ADRIAN CASTRO
Sewer availability Cleared 3/11/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/11/2021 No Result Entered GREG ALLTON
Footing/Foundation/Slab 5/14/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 5/14/2021 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 5/21/2021 Approved RICHARD DOCKUS
Wood Frame 5/21/2021 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 5/25/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 5/25/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 6/7/2021 Approved RICHARD DOCKUS
Insulation 6/8/2021 Not Ready for Inspection ALAN MORELOS
Insulation 6/9/2021 Approved ALAN MORELOS
Drywall Nailing 6/15/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/21/2021 Approved JAVIER RAMOS JR
Shower Pan 6/25/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 7/1/2021 Approved RICHARD DOCKUS
ELECTRICAL-Final 8/10/2021 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 8/10/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 8/10/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/1/2021 Approved CHRISTOPHE COCHRAN
Final 9/1/2021 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 9/1/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 9/1/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 9/1/2021 Approved CHRISTOPHE COCHRAN