2730-2730 1/2 N IVAN CT 90039
Certificate Information: 2730-2730 1/2 N IVAN CT 90039
- Application / Permit
- 21014-20000-00564
- Plan Check / Job No.
- B21VN01520
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (E ) 19'7" X 19'6" ATTACHED GARAGE TO (E) SFD TO ACCESSORY DWELLING UNIT PER GCS 65852.2.(E)(1)(A), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Current Status
- CofO Issued on 1/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | RARES BODEA |
| Corrections Issued | 2/27/2021 | RARES BODEA |
| Quality Review Completed | 3/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | RARES BODEA |
| Applicant returned to address corrections | 8/24/2022 | RARES BODEA |
| Plan Check Approved | 4/14/2023 | RARES BODEA |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 1/17/2024 | LILIANA PORTILLO |
| Permit Finaled | 1/28/2024 | DEROLD HAUFF |
| CofO Issued | 1/28/2024 | DEROLD HAUFF |
| Permit Finaled | 1/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 3/7/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 3/7/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 3/15/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | CINDY QI |
| Sewer availability | Cleared | 3/15/2022 | CINDY QI |
| Distance to fire station | Cleared | 4/29/2022 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 4/29/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 8/24/2022 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 8/24/2022 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/1/2023 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 11/15/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 11/15/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 11/15/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 11/15/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/15/2023 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 11/15/2023 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 11/16/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 11/20/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 11/20/2023 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/22/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/22/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/21/2023 | Approved | BRENDAN MORELLI |
| Final | 12/21/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Final | 12/21/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 12/21/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV No Gas | BRENDAN MORELLI |
| Smoke Detectors | 12/21/2023 | Approved | BRENDAN MORELLI |
| Green Building Final | 12/28/2023 | Approved | RICHARD DOCKUS |
| HVAC-Final | 12/28/2023 | Approved | RICHARD DOCKUS |
| Final | 1/11/2024 | OK to Issue CofO | LILIANA PORTILLO |