1726 N LUCILE AVE 90026

Certificate Information: 1726 N LUCILE AVE 90026

Application / Permit
21014-20000-00559
Plan Check / Job No.
B21VN01512
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE PORTION OF (E) PATIO COVER, IRR. SHAPED ADDITION (13'- 0 1/2" x 22'-11") TO THE REAR OF (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 5/21/2021
Issuing Office
Current Status
CofO Issued on 1/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 SEAN SHAHMIRI
Corrections Issued 2/28/2021 SEAN SHAHMIRI
Quality Review Completed 3/12/2021 OMID HEDAYAT
Applicant returned to address corrections 3/14/2021 SEAN SHAHMIRI
Building Plans Picked Up 3/15/2021 APPLICANT
Applicant returned to address corrections 4/14/2021 SEAN SHAHMIRI
Applicant returned to address corrections 5/7/2021 SEAN SHAHMIRI
Plan Check Approved 5/10/2021 SEAN SHAHMIRI
Issued 5/21/2021 APPLICANT
CofO in Progress 1/14/2022 THOMAS LOGRASSO
Permit Finaled 1/31/2022 DEROLD HAUFF
CofO Issued 1/31/2022 DEROLD HAUFF
Permit Finaled 1/31/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/15/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 3/15/2021 JEANIE LAM
Sewer availability Cleared 3/15/2021 JEANIE LAM
Grading Pre-Inspection Cleared 4/13/2021 SEAN SHAHMIRI
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG

Contact Information

Architect Perella,, Ryan Adam; Lic. No.: C30833 606 N LARCHMONT BLVD # 4A      LOS ANGELES, CA 90004
Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/1/2021 Conditional Approval THOMAS LOGRASSO
PLUMBING-Rough 6/7/2021 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 6/10/2021 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 7/9/2021 Partial Approval JUSTIN CURTIS
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval JUSTIN CURTIS
PLUMBING-Rough 7/9/2021 Partial Approval JUSTIN CURTIS
BUILDING-Rough-Frame 7/22/2021 Not Ready for Inspection THOMAS LOGRASSO
Deputy Wood Construction 7/22/2021 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 7/22/2021 Corrections Issued THOMAS LOGRASSO
Green Building Rough 7/22/2021 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 7/22/2021 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 7/22/2021 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/28/2021 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 7/28/2021 Approved THOMAS LOGRASSO
Green Building Rough 7/28/2021 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 7/28/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 7/28/2021 Approved THOMAS LOGRASSO
Insulation 8/16/2021 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 8/16/2021 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 8/18/2021 Approved THOMAS LOGRASSO
Green Building Rough 8/18/2021 Approved THOMAS LOGRASSO
Insulation 8/18/2021 Approved THOMAS LOGRASSO
Drywall Nailing 8/24/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/24/2021 Partial Approval THOMAS LOGRASSO
Shower Pan 8/27/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 9/3/2021 Approved THOMAS LOGRASSO
Gas Test 10/19/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 11/23/2021 Corrections Issued THOMAS LOGRASSO
Final 11/23/2021 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 11/23/2021 Approved THOMAS LOGRASSO
Green Building Final 11/23/2021 Corrections Issued THOMAS LOGRASSO
HVAC-Final 11/23/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 11/23/2021 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/23/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 12/8/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 12/8/2021 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 12/8/2021 Approved THOMAS LOGRASSO
Final 1/14/2022 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 1/14/2022 Approved THOMAS LOGRASSO