6709 N ORION AVE 91406
Certificate Information: 6709 N ORION AVE 91406
- Application / Permit
- 21014-20000-00554
- Plan Check / Job No.
- B21VN01489
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO ADD (1) BATHROOM/LAUNDRY AND 38' 10" X 9' 9" ADDITION TO SIDE OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 2/27/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/25/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 6/28/2021 | APPLICANT |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 12/30/2021 | RICHARD DOCKUS |
| CofO Issued | 3/14/2022 | MICHAEL SMITH |
| Permit Finaled | 3/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/18/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/20/2021 | GABRIEL ROBLES |
| ZI | Cleared | 6/15/2021 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/20/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/20/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/23/2021 | Partial Approval | AMY COLIN |
| Insulation | 7/23/2021 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 9/1/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/1/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 9/1/2021 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 9/1/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| MERV13>=Rough | 9/1/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/1/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/9/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/9/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 9/9/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 9/9/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/13/2021 | Approved | ADAM ESCOTO |
| HVAC-Rough | 9/13/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 9/17/2021 | Not Ready for Inspection | AMY COLIN |
| Interior/Exterior Lathing | 9/21/2021 | Approved | AMY COLIN |
| Insulation | 9/24/2021 | Approved | AMY COLIN |
| Shower Pan | 9/24/2021 | Corrections Issued | AMY COLIN |
| Drywall Nailing | 9/29/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/29/2021 | Approved | AMY COLIN |
| Shower Pan | 9/29/2021 | Approved | AMY COLIN |
| ELECTRICAL-Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| Final | 12/15/2021 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/15/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| HVAC-Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| MERV13>=Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 12/15/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/15/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 12/15/2021 | Approved | RICHARD DOCKUS |
| Final | 12/29/2021 | OK to Issue CofO | RICHARD DOCKUS |