11918 W OXNARD ST 91607
Certificate Information: 11918 W OXNARD ST 91607
- Application / Permit
- 21014-20000-00553
- Plan Check / Job No.
- B21VN01486
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 14'10" x 10' ADDITION AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2021 | JEFFREY TANGONAN |
| Corrections Issued | 2/23/2021 | JEFFREY TANGONAN |
| Issued | 6/21/2021 | APPLICANT |
| Building Plans Picked Up | 6/23/2021 | APPLICANT |
| CofO in Progress | 5/3/2022 | ARAM AVEDISIAN |
| Permit Finaled | 8/6/2022 | DEROLD HAUFF |
| CofO Issued | 8/6/2022 | DEROLD HAUFF |
| Permit Finaled | 8/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/27/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/3/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/9/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/10/2021 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 11/16/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 12/14/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/14/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 12/17/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/20/2021 | Partial Approval | DAVID MATSON |
| Gas Test | 12/20/2021 | Approved | DAVID MATSON |
| Green Building Rough | 12/20/2021 | Approved | DAVID MATSON |
| MERV13>=Rough | 12/20/2021 | Approved | DAVID MATSON |
| HVAC-Rough | 12/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 12/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/27/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/29/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/29/2021 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 12/30/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 1/18/2022 | Approved | KRISTEN CAUSEY |
| Gas Test | 1/21/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | ARAM AVEDISIAN |
| Final | 3/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/3/2022 | Approved | ARAM AVEDISIAN |
| Green Building Final | 3/3/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 3/3/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 3/3/2022 | Approved | ARAM AVEDISIAN |
| Final | 3/21/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 4/14/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Final | 5/3/2022 | OK to Issue CofO | ARAM AVEDISIAN |