6550 N SHELTONDALE AVE 91307

Certificate Information: 6550 N SHELTONDALE AVE 91307

Application / Permit
21014-20000-00550
Plan Check / Job No.
B21VN01483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
47'-2" x 49'-7" IRR. SHAPED ADDITION & REMODEL TO (E) SINGLE FAMILY DWELLLING W/ ATT. GARAGE; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 11/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 SEAN SHAHMIRI
Corrections Issued 3/2/2021 SEAN SHAHMIRI
Quality Review Completed 3/15/2021 OMID HEDAYAT
Building Plans Picked Up 3/19/2021 APPLICANT
Applicant returned to address corrections 6/25/2021 SEAN SHAHMIRI
Plan Check Approved 6/25/2021 SEAN SHAHMIRI
Issued 6/25/2021 APPLICANT
CofO in Progress 11/7/2022 TROY SANDERS
Permit Finaled 11/14/2022 JOHN JANSON
CofO Issued 11/14/2022 JOHN JANSON
Permit Finaled 11/14/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/29/2021 GABRIEL ROBLES
Sewer availability Cleared 4/29/2021 GABRIEL ROBLES
Low Impact Development Cleared 6/18/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/21/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/12/2021 Partial Approval TROY SANDERS
Footing/Foundation/Slab 7/16/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 10/22/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 10/22/2021 Approved TROY SANDERS
Green Building Rough 10/22/2021 Not Ready for Inspection TROY SANDERS
HVAC-Rough 10/22/2021 Approved TROY SANDERS
PLUMBING-Rough 10/22/2021 Approved TROY SANDERS
Green Building Rough 10/27/2021 Approved ROBERT GOLD
Insulation 10/27/2021 Approved ROBERT GOLD
Interior/Exterior Lathing 10/27/2021 Partial Approval ROBERT GOLD
Drywall Nailing 11/4/2021 Partial Approval JESUS PINEDA
Drywall Nailing 11/18/2021 Approved TROY SANDERS
Interior/Exterior Lathing 11/18/2021 Approved TROY SANDERS
Shower Pan 11/18/2021 Approved TROY SANDERS
ELECTRICAL-Final 7/13/2022 Approved TROY SANDERS
HVAC-Final 7/13/2022 Approved TROY SANDERS
PLUMBING-Final 7/13/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 11/7/2022 Approved TROY SANDERS
Final 11/7/2022 OK to Issue CofO TROY SANDERS
Green Building Final 11/7/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 11/7/2022 Approved TROY SANDERS