8636 W WENTWORTH ST 91040
Certificate Information: 8636 W WENTWORTH ST 91040
- Application / Permit
- 21014-20000-00541
- Plan Check / Job No.
- B21VN01423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 1ST AND 2ND STORY ADDITION TO (E) 1-STORY, IRREGULAR SHAPED (36'-6" X 43'-0") SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/11/2021
- Issuing Office
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | COLIN LOREDO |
| Corrections Issued | 3/2/2021 | COLIN LOREDO |
| Quality Review Completed | 3/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/17/2021 | APPLICANT |
| Applicant returned to address corrections | 8/24/2021 | COLIN LOREDO |
| Plan Check Approved | 9/2/2021 | COLIN LOREDO |
| Issued | 9/11/2021 | APPLICANT |
| CofO in Progress | 10/26/2022 | MATTHEW NELSON |
| CofO Issued | 10/29/2022 | MICHAEL SMITH |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | GABRIEL ROBLES |
| Permit | Cleared | 3/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/22/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 5/6/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 8/10/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/12/2021 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 8/24/2021 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 8/24/2021 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/20/2021 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 9/27/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 9/27/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/27/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2021 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 10/26/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/29/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/29/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 10/29/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/2/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 11/2/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/2/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/4/2021 | Approved | MATTHEW NELSON |
| Insulation | 11/9/2021 | Conditional Approval | WILLIAM WREN |
| Drywall Nailing | 11/15/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 11/15/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/19/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 11/19/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/10/2021 | Approved | MATTHEW NELSON |
| Service/Power Release | 3/2/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/21/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Drywall Nailing | 10/17/2022 | Approved | MATTHEW NELSON |
| Final | 10/17/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 10/17/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 10/17/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 10/26/2022 | Approved | MATTHEW NELSON |
| Final | 10/26/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 10/26/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 10/26/2022 | Approved | MATTHEW NELSON |