13107 W ROSE AVE 90066
Certificate Information: 13107 W ROSE AVE 90066
- Application / Permit
- 21014-20000-00506
- Plan Check / Job No.
- B21VN01333
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 14'-5" X 38-3" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD FOR TO ENLARGE BEDROOM, (N) CLOSET, (N) BATHROOM AND (N) DEN. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/23/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/6/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 10/5/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 3/14/2025 | MICHAEL ALLEN |
| CofO Issued | 3/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/8/2021 | BRIAN MILLER |
| Sewer availability | Cleared | 3/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 8/31/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/14/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 10/5/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Ash Construction And Development Inc; Lic. No.: 1076076-B | 289 S ROBERTSON BLVD UNIT 215 BEVERLY HILLS, CA 90211 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/22/2021 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 1/6/2022 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 1/6/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 1/10/2022 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/19/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 1/21/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 1/21/2022 | Approved | DEANDRE HOFFMAN |
| Insulation | 1/25/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/31/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | ENRIQUE MIRELES |
| Final | 2/22/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/22/2022 | Approved | ENRIQUE MIRELES |
| Green Building Final | 2/22/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 2/22/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/22/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/22/2022 | Approved | ENRIQUE MIRELES |
| Final | 3/8/2022 | Corrections Issued | DAVID FEILER |
| Final | 3/22/2022 | Partial Approval | PATRICK QUALEY |
| Final | 3/13/2025 | OK to Issue CofO | MICHAEL ALLEN |