7728 N AMESTOY AVE 91406

Certificate Information: 7728 N AMESTOY AVE 91406

Application / Permit
21014-20000-00503
Plan Check / Job No.
B21VN01328
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
19'-0" X 25'-0" ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 ARTIN ZARUKIAN
Corrections Issued 2/20/2021 ARTIN ZARUKIAN
Applicant returned to address corrections 3/8/2021 ARTIN ZARUKIAN
Applicant returned to address corrections 3/22/2021 ARTIN ZARUKIAN
Plan Check Approved 4/13/2021 ARTIN ZARUKIAN
Issued 4/15/2021 APPLICANT
Building Plans Picked Up 4/26/2021 APPLICANT
CofO in Progress 4/21/2022 RAUL OLAGI
CofO Issued 4/26/2022 RONALD MYRICK
Permit Finaled 4/26/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 3/3/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/10/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Anaya Carlos; Lic. No.: 1034169-B 6936 JUMILLA AVE      WINNETKA, CA 91306

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/21/2021 Corrections Issued KIM BEAUCHAMP
Sewer 5/21/2021 Approved KIM BEAUCHAMP
Underground Mechanical 5/21/2021 Approved KIM BEAUCHAMP
Excavation/Setback/Form/Re-Bar 5/27/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 7/12/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 7/12/2021 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 7/12/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 7/12/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 7/12/2021 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 8/24/2021 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 8/24/2021 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 8/24/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/1/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 9/1/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Approved JENNIFER RABUCHIN
Green Building Rough 9/1/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 9/1/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 9/1/2021 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 9/13/2021 Approved AMY COLIN
Interior/Exterior Lathing 9/13/2021 Partial Approval AMY COLIN
Drywall Nailing 9/28/2021 Approved AMY COLIN
ELECTRICAL-Rough 9/28/2021 Approved AMY COLIN
Green Building Rough 9/28/2021 Approved AMY COLIN
PLUMBING-Rough 9/28/2021 Approved AMY COLIN
Final 1/20/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/20/2022 Approved RAUL OLAGI
Green Building Final 1/20/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/20/2022 Approved RAUL OLAGI
Final 1/26/2022 Not Ready for Inspection RAUL OLAGI
Green Building Final 1/26/2022 Not Ready for Inspection RAUL OLAGI
Final 2/14/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/14/2022 Approved RAUL OLAGI
Final 4/21/2022 OK to Issue CofO RAUL OLAGI