17552 W HAMLIN ST 91406
Certificate Information: 17552 W HAMLIN ST 91406
- Application / Permit
- 21014-20000-00487
- Plan Check / Job No.
- B21VN01290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF TWO BEDROOMS AND A MUD ROOM TO THE (E) SFD. AND TRELLIS (18'-0"x38'-4")
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/18/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| Plan Check Approved | 6/29/2021 | MOHAMMAD ESMAILI |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 4/25/2022 | SEAN HAUPT |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 4/30/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 5/24/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/25/2021 | GABRIEL ROBLES |
Contact Information
| Architect | Bryant,, Gregory Nathan; Lic. No.: C34037 | 237 NELLORA STREET CAMARILLO, CA 93010 |
| Contractor | David Munyer Construction; Lic. No.: 408227-B | 22710 JAMESON DRIVE CALABASAS, CA 91302 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2021 | Partial Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 9/9/2021 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 9/10/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/24/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/24/2021 | Partial Approval | STEVEN BACK |
| Insulation | 9/28/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 9/30/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/23/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/7/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 12/7/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/13/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/13/2021 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 12/13/2021 | Approved | SEAN HAUPT |
| Insulation | 12/15/2021 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/22/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 12/28/2021 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 1/21/2022 | Approved | SEAN HAUPT |
| Shower Pan | 1/21/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 2/10/2022 | Approved | SEAN HAUPT |
| Final | 2/10/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 2/10/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 2/10/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 2/10/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 2/10/2022 | Approved | SEAN HAUPT |
| Final | 4/22/2022 | OK to Issue CofO | SEAN HAUPT |