17552 W HAMLIN ST 91406

Certificate Information: 17552 W HAMLIN ST 91406

Application / Permit
21014-20000-00487
Plan Check / Job No.
B21VN01290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF TWO BEDROOMS AND A MUD ROOM TO THE (E) SFD. AND TRELLIS (18'-0"x38'-4")
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 5/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 MOHAMMAD ESMAILI
Corrections Issued 2/18/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 2/24/2021 APPLICANT
Plan Check Approved 6/29/2021 MOHAMMAD ESMAILI
Issued 6/30/2021 APPLICANT
CofO in Progress 4/25/2022 SEAN HAUPT
Permit Finaled 5/14/2022 MICHAEL SMITH
CofO Issued 5/14/2022 MICHAEL SMITH
Permit Finaled 5/14/2022 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 4/30/2021 LAUREN PADICK
Low Impact Development Cleared 5/24/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/24/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/25/2021 GABRIEL ROBLES
Sewer availability Cleared 5/25/2021 GABRIEL ROBLES

Contact Information

Architect Bryant,, Gregory Nathan; Lic. No.: C34037 237 NELLORA STREET      CAMARILLO, CA 93010
Contractor David Munyer Construction; Lic. No.: 408227-B 22710 JAMESON DRIVE      CALABASAS, CA 91302
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2021 Partial Inspection STEVEN BACK
Deputy Drilled-In Anchors 9/9/2021 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 9/10/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 9/24/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 9/24/2021 Partial Approval STEVEN BACK
Insulation 9/28/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval STEVEN BACK
Interior/Exterior Lathing 9/30/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/23/2021 Not Ready for Inspection SEAN HAUPT
Green Building Rough 11/23/2021 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection SEAN HAUPT
Green Building Rough 12/7/2021 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 12/7/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/13/2021 Approved SEAN HAUPT
Green Building Rough 12/13/2021 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 12/13/2021 Approved SEAN HAUPT
Insulation 12/15/2021 Approved SEAN HAUPT
Drywall Nailing 12/22/2021 Approved JUSTIN HAWLEY
Drywall Nailing 12/28/2021 Partial Approval RYAN SALAZAR
Service/Power Release 1/21/2022 Approved SEAN HAUPT
Shower Pan 1/21/2022 Approved SEAN HAUPT
ELECTRICAL-Final 2/10/2022 Approved SEAN HAUPT
Final 2/10/2022 Corrections Issued SEAN HAUPT
Green Building Final 2/10/2022 Approved SEAN HAUPT
HVAC-Final 2/10/2022 Approved SEAN HAUPT
PLUMBING-Final 2/10/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 2/10/2022 Approved SEAN HAUPT
Final 4/22/2022 OK to Issue CofO SEAN HAUPT