1935 1/2 N ECHO PARK AVE 90026
Certificate Information: 1935 1/2 N ECHO PARK AVE 90026
- Application / Permit
- 21014-20000-00466
- Plan Check / Job No.
- B21VN01237
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH 2ND STORY ADDITION PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | COLIN LOREDO |
| Corrections Issued | 2/23/2021 | COLIN LOREDO |
| Quality Review Completed | 3/4/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Applicant returned to address corrections | 3/30/2021 | COLIN LOREDO |
| Plan Check Approved | 7/6/2021 | COLIN LOREDO |
| Issued | 8/6/2021 | APPLICANT |
| CofO in Progress | 1/4/2023 | THOMAS LOGRASSO |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/8/2021 | MIGUEL GAMBOA |
| Address approval | Cleared | 4/8/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/8/2021 | RENZ SORIANO |
| Tenant Habitability Plan | Cleared | 4/16/2021 | RICHARD BRINSON |
| Hydrant and Access approval | Cleared | 5/19/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Pacific Coast Developers; Lic. No.: 888234-B | 5249 BECKFORD AVENUE TARZANA, CA 91356 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 10/5/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/19/2021 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 11/1/2021 | Partial Approval | RUBEN SALAS |
| Underground Mechanical | 12/6/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/21/2021 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/21/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/21/2021 | Corrections Issued | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 12/21/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/5/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 1/5/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 1/5/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/5/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 2/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/2/2022 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 3/2/2022 | Partial Inspection | ADAM ESCOTO |
| BUILDING-Rough-Frame | 3/15/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 3/15/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 3/22/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/31/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/6/2022 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 11/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Underground Mechanical | 11/7/2022 | Partial Approval | THOMAS LOGRASSO |
| Final | 11/29/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 11/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 11/29/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/22/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 12/22/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 12/22/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 1/4/2023 | OK to Issue CofO | THOMAS LOGRASSO |