10929 N RESEDA BLVD 91326
Certificate Information: 10929 N RESEDA BLVD 91326
- Application / Permit
- 21014-20000-00456
- Plan Check / Job No.
- B21VN01226
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 12'-6" X 19'-6" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 3/13/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/9/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/21/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 3/30/2023 | DAVID SCANTLIN |
| Permit Finaled | 5/3/2023 | JOHN JANSON |
| CofO Issued | 5/3/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/11/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/12/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2022 | Corrections Issued | JEFFREY PARD |
| Deputy Drilled-In Anchors | 7/7/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 7/14/2022 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 7/19/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 7/25/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 8/1/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 9/19/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 9/19/2022 | Not Ready for Inspection | SEAN HAUPT |
| Insulation | 10/3/2022 | No Access for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | JOHN KIDWELL |
| Final | 1/13/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 1/13/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 1/13/2023 | Approved | JOHN KIDWELL |
| Final | 3/29/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 3/29/2023 | Approved | DAVID SCANTLIN |