17443 W VALERIO ST 91406
Certificate Information: 17443 W VALERIO ST 91406
- Application / Permit
- 21014-20000-00446
- Plan Check / Job No.
- B21VN01206
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO THE (E) SFD. WITH (14'-7"X31'-8") IN THE FRONT AND ENCLOSING PATIO (9'-0"X13'-6") IN THE REAR AND DEMOLISH PORTION OF THE HOUSE IN THE BACK ( 8'-0"X13'-3"). ALL WORK PER ENGINEERING. FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 8/4/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/18/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/4/2021 | OMAR GARNICA |
| Issued | 8/4/2021 | APPLICANT |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| CofO in Progress | 2/23/2023 | ROBERT GOLD |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
| CofO Issued | 3/2/2023 | MICHAEL SMITH |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/10/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 7/14/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/15/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos M; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/12/2021 | Partial Inspection | JACK KARGODORIAN |
| Underground Mechanical | 10/12/2021 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 10/20/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 11/3/2021 | Approved | RAUL OLAGI |
| Sewer | 11/3/2021 | Approved | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/4/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/8/2022 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 6/3/2022 | Conditional Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/6/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 6/6/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/1/2022 | Not Ready for Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 7/1/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 7/1/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Rough | 7/19/2022 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| HVAC-Rough | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| Insulation | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/2/2022 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 8/12/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/12/2022 | Approved | ALAN MORELOS |
| Shower Pan | 8/12/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 2/10/2023 | Corrections Issued | RAUL OLAGI |
| Final | 2/10/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/10/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 2/10/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/10/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 2/10/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/21/2023 | Approved | ROBERT GOLD |
| Final | 2/21/2023 | OK to Issue CofO | ROBERT GOLD |
| HVAC-Final | 2/21/2023 | Approved | ROBERT GOLD |
| PLUMBING-Final | 2/21/2023 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | ROBERT GOLD |