1233 N BIENVENEDA AVE 90272
Certificate Information: 1233 N BIENVENEDA AVE 90272
- Application / Permit
- 21014-20000-00438
- Plan Check / Job No.
- B21VN01195
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 1ST, 2ND & 3RD STORY ADDITION TO (E) IRREGULAR SHAPED SINGLE FAMILY DWELLING W/ ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 2/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | COLIN LOREDO |
| Corrections Issued | 2/9/2021 | COLIN LOREDO |
| Quality Review Completed | 2/10/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 2/16/2021 | APPLICANT |
| Applicant returned to address corrections | 3/1/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 4/22/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 5/14/2021 | COLIN LOREDO |
| Plan Check Approved | 6/4/2021 | COLIN LOREDO |
| Issued | 6/4/2021 | APPLICANT |
| CofO in Progress | 10/5/2023 | KENNETH NAGLE |
| Permit Finaled | 2/27/2024 | DANIEL ORRANTE |
| CofO Issued | 2/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/2/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 3/2/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 3/2/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 3/2/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 3/16/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | TRACY TATE |
| Sewer availability | Cleared | 3/16/2021 | TRACY TATE |
| Hydrant and Access approval | Cleared | 4/21/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/19/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/19/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 5/19/2021 | MAHELET GEBEYHU |
| Coastal Zone | Cleared | 5/21/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 5/21/2021 | DENZEL HENDERSON |
Contact Information
| Architect | Parsa,, Ali; Lic. No.: C31447 | 410 S BARRINGTON AVE # 106 LOS ANGELES, CA 90049 |
| Contractor | Arya Group Inc; Lic. No.: 694649-B | 10490 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Moore,, Elham; Lic. No.: C79263 | P.O. BOX 280062 NORTHRIDGE, CA 91328 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 8/19/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/19/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/23/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 8/23/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 9/17/2021 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 10/18/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/2/2021 | Partial Inspection | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/8/2021 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 1/7/2022 | Partial Approval | ANDREW NAVE |
| FLOOD-Proofing Certificate | 2/14/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 6/23/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 6/30/2022 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 7/5/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 7/22/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 7/22/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Insulation | 7/22/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 7/22/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/11/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 8/11/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 9/1/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 9/29/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 9/30/2022 | Conditional Approval | BRENDAN LOONEY |
| Wood Frame | 10/13/2022 | Partial Approval | EVAN COOPER |
| Insulation | 10/20/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 11/1/2022 | Approved | BRENDAN LOONEY |
| Green Building Rough | 11/1/2022 | Approved | BRENDAN LOONEY |
| Shower Pan | 11/1/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/8/2022 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 3/9/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 5/5/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/9/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/11/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/11/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/11/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/15/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 5/15/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/15/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/15/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/17/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/24/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/24/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 5/26/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/26/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 5/26/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 5/26/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 5/31/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/5/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 6/5/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/21/2023 | Corrections Issued | EVAN COOPER |
| Final | 9/25/2023 | Corrections Issued | ARAM AVEDISIAN |
| Final | 10/5/2023 | OK to Issue CofO | KENNETH NAGLE |