901 N KENMORE AVE 90029

Certificate Information: 901 N KENMORE AVE 90029

Application / Permit
21014-20000-00435
Plan Check / Job No.
B21VN01190
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTIC TO HABITABLE SPACE TO 2ND STORY ADDITION , REPLACE (E) WINDOWS
Permit Issued
Issued on 6/3/2021
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 CHON CHIO KUO
Corrections Issued 3/11/2021 CHON CHIO KUO
Quality Review Completed 3/16/2021 STEVEN KIM
Building Plans Picked Up 3/17/2021 APPLICANT
Applicant returned to address corrections 4/12/2021 CHON CHIO KUO
Applicant returned to address corrections 4/27/2021 CHON CHIO KUO
Plan Check Approved 5/10/2021 CHON CHIO KUO
Issued 6/3/2021 APPLICANT
CofO in Progress 6/20/2022 FREDDIE RIVERA
Permit Finaled 7/28/2022 DEROLD HAUFF
CofO Issued 7/28/2022 DEROLD HAUFF
Permit Finaled 7/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/23/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/24/2021 WALLIE JONG
Sewer availability Cleared 4/7/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2021 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 11/9/2021 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/9/2021 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/9/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/18/2021 Not Ready for Inspection ROBERT VORHIS
Green Building Rough 11/18/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 1/6/2022 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/6/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 1/6/2022 Approved ALIZAH MAYAGOITIA
Insulation 1/6/2022 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 1/6/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Corrections Issued ALIZAH MAYAGOITIA
Insulation 1/14/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/2/2022 Approved AMY COLIN
Final 2/9/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 2/9/2022 Approved STUART CHAPMAN
Shower Pan 2/16/2022 Partial Inspection AMY COLIN
Shower Pan 2/25/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 3/2/2022 Partial Approval ADAM ESCOTO
Interior/Exterior Lathing 3/4/2022 Approved AMY COLIN
PLUMBING-Rough 3/4/2022 Approved AMY COLIN
BUILDING-Rough-Frame 3/10/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 5/10/2022 Approved FREDDIE RIVERA
HVAC-Final 5/10/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 5/11/2022 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 6/6/2022 Partial Inspection FREDDIE RIVERA
Final 6/6/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 6/6/2022 Partial Inspection FREDDIE RIVERA
HVAC-Final 6/6/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 6/6/2022 Partial Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Not Ready FREDDIE RIVERA
BUILDING-Rough-Frame 6/13/2022 Approved FREDDIE RIVERA
Final 6/13/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 6/13/2022 Approved FREDDIE RIVERA
HVAC-Final 6/13/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 6/13/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 6/13/2022 Approved FREDDIE RIVERA
Final 6/17/2022 OK to Issue CofO FREDDIE RIVERA
HVAC-Final 6/17/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Approved FREDDIE RIVERA