523 N FORMOSA AVE 90036

Certificate Information: 523 N FORMOSA AVE 90036

Application / Permit
21014-20000-00433
Plan Check / Job No.
B21VN01185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-4" x 16'-4" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH 27'-10" x 14'-2" IRREGULAR SHAPED ADDITION AND EXTERIOR STAIRS ACCESS TO A ROOF DECK PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 SARKIS HARABEDIAN
Corrections Issued 2/20/2021 SARKIS HARABEDIAN
Quality Review Completed 2/26/2021 STEVEN KIM
Plan Check Approved 6/29/2021 SARKIS HARABEDIAN
Issued 6/29/2021 APPLICANT
Building Plans Picked Up 6/30/2021 APPLICANT
CofO in Progress 3/11/2022 CHRIS CHRISTENSEN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/30/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/30/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 4/30/2021 JEANIE LAM
Sewer availability Cleared 4/30/2021 JEANIE LAM
Construction near power lines Cleared 5/12/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 6/21/2021 KURT CORRAL

Contact Information

Contractor L E Construction & Development Inc; Lic. No.: 1051866-B 7111 SANTA MONICA BLVD   SUITE B-272    LOS ANGELES, CA 90046
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/12/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 7/12/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 7/12/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 7/14/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/16/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 8/27/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 9/2/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/2/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/4/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/4/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 10/4/2021 Approved CHRIS CHRISTENSEN
Insulation 10/4/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 10/4/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/13/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/19/2021 Approved ARTHUR SARGSYAN
Final 12/13/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 12/13/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 12/13/2021 Approved CHRIS CHRISTENSEN
Final 12/20/2021 Corrections Issued CRAIG DAVIS
Green Building Final 12/20/2021 Corrections Issued CRAIG DAVIS
Final 12/28/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 12/28/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 1/4/2022 Approved CHRIS CHRISTENSEN
Final 1/4/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/4/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 1/4/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/4/2022 Approved CHRIS CHRISTENSEN
Final 1/10/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 1/13/2022 Conditional Approval CHRIS CHRISTENSEN
Final 3/10/2022 OK to Issue CofO CHRIS CHRISTENSEN