523 N FORMOSA AVE 90036
Certificate Information: 523 N FORMOSA AVE 90036
- Application / Permit
- 21014-20000-00433
- Plan Check / Job No.
- B21VN01185
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-4" x 16'-4" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH 27'-10" x 14'-2" IRREGULAR SHAPED ADDITION AND EXTERIOR STAIRS ACCESS TO A ROOF DECK PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- CofO Issued on 4/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 2/20/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 2/26/2021 | STEVEN KIM |
| Plan Check Approved | 6/29/2021 | SARKIS HARABEDIAN |
| Issued | 6/29/2021 | APPLICANT |
| Building Plans Picked Up | 6/30/2021 | APPLICANT |
| CofO in Progress | 3/11/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
| CofO Issued | 4/1/2022 | DEROLD HAUFF |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 4/30/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/30/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 5/12/2021 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 6/21/2021 | KURT CORRAL |
Contact Information
| Contractor | L E Construction & Development Inc; Lic. No.: 1051866-B | 7111 SANTA MONICA BLVD SUITE B-272 LOS ANGELES, CA 90046 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/12/2021 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/16/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 8/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/4/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/4/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/4/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 10/4/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/13/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/19/2021 | Approved | ARTHUR SARGSYAN |
| Final | 12/13/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 12/13/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 12/13/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 12/20/2021 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 12/20/2021 | Corrections Issued | CRAIG DAVIS |
| Final | 12/28/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 12/28/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/4/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 1/4/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/4/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/4/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/4/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 1/10/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 1/13/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Final | 3/10/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |