1354 3/4 S MEADOWBROOK AVE 90019

Certificate Information: 1354 3/4 S MEADOWBROOK AVE 90019

Application / Permit
21014-20000-00416
Plan Check / Job No.
B21VN01079
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) W/ 2ND FLOOR ADDITION AND ADD STORAGE . ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/10/2022
Issuing Office
Current Status
CofO Corrected on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 COLIN LOREDO
Corrections Issued 2/23/2021 COLIN LOREDO
Quality Review Completed 3/8/2021 OMID HEDAYAT
Building Plans Picked Up 3/11/2021 APPLICANT
Plan Check Approved 11/10/2021 COLIN LOREDO
Issued 1/10/2022 APPLICANT
CofO in Progress 1/31/2025 ARTHUR NEGRETE
No Progress 2/9/2025 DEROLD HAUFF
CofO in Progress 2/9/2025 DEROLD HAUFF
Re-Activate Permit 2/13/2025 DEROLD HAUFF
CofO Issued-Status Void 2/13/2025 DEROLD HAUFF
Permit Finaled-Status Void 2/13/2025 DEROLD HAUFF
Permit Finaled 2/13/2025 DEROLD HAUFF
CofO Corrected 2/13/2025 DEROLD HAUFF
Permit Finaled 2/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/9/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/15/2021 RENZ SORIANO
Construction near power lines Cleared 6/29/2021 RIDWAN HARDY
Sewer availability Cleared 7/15/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/8/2021 THAN WIN

Contact Information

Architect Newbern,, Walter Pedro; Lic. No.: C22914 1010 NO. MADISON AVENUE      PASADENA, CA 91104
Contractor Owner-Builder       ,
Engineer Tsai,, Willy Y; Lic. No.: C35589 1545 RUBIO DR      SAN MARINO, CA 91108

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/10/2022 Approved JOSE AVILA
METHANE-Barrier 3/10/2022 Approved JOSE AVILA
METHANE-Subgrade 3/10/2022 Approved JOSE AVILA
PLUMBING-Rough 3/10/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 3/16/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/21/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Corrections Issued JOSE AVILA
Sewer 2/2/2023 Partial Approval JOSE AVILA
Underground Mechanical 2/7/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 3/29/2023 Partial Approval JOSE AVILA
Underground Mechanical 3/31/2023 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/17/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/23/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Approved JOSE AVILA
PLUMBING-Rough 8/4/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/16/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 8/16/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/21/2023 Corrections Issued JOSE AVILA
HVAC-Rough 9/21/2023 Not Ready for Inspection JOSE AVILA
METHANE-Rough 9/21/2023 Approved JOSE AVILA
ELECTRICAL-Rough 10/10/2023 Approved JOSE AVILA
PLUMBING-Rough 10/10/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 10/18/2023 Approved JOSE AVILA
Green Building Rough 10/18/2023 Approved JOSE AVILA
HVAC-Rough 10/18/2023 Approved JOSE AVILA
Drywall Nailing 10/30/2023 Approved JOSE AVILA
Insulation 10/30/2023 Approved JOSE AVILA
Interior/Exterior Lathing 1/2/2024 Approved JOSH MEISTER
Shower Pan 1/2/2024 Approved JOSH MEISTER
Final 3/12/2024 Corrections Issued STUART CHAPMAN
Green Building Final 3/12/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/12/2024 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/12/2024 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/12/2024 Approved STUART CHAPMAN
Service/Power Release 5/31/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 6/18/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 8/20/2024 Approved ARTHUR NEGRETE
Gas Test 9/18/2024 Approved ARTHUR NEGRETE
Service/Power Release 9/18/2024 Approved ARTHUR NEGRETE
HVAC-Final 10/18/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 10/18/2024 Approved ARTHUR NEGRETE
Final 11/18/2024 Partial Approval ARTHUR NEGRETE
Final 12/18/2024 Conditional Approval ARTHUR NEGRETE
Final 1/30/2025 OK to Issue CofO ARTHUR NEGRETE