7512 N BALBOA BLVD 91406

Certificate Information: 7512 N BALBOA BLVD 91406

Application / Permit
21014-20000-00413
Plan Check / Job No.
B21VN01066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 27'-9" X 19'-2" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE A (N) MASTER BEDROOM, MASTER BATHROOM, AND WALK IN CLOSET, INTERIOR REMODEL THE (E) SFD TO REMODEL KITCHEN , BATHROOM , LAUNDRY , LIVING ROOM , DINING ROOM , (2) BEDROOMS, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/27/2021
Issuing Office
Valley
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 RARES BODEA
Corrections Issued 3/12/2021 RARES BODEA
Applicant returned to address corrections 9/29/2021 RAPHAEL ROSAS
Plan Check Approved 10/6/2021 RAPHAEL ROSAS
Building Plans Picked Up 10/7/2021 APPLICANT
Issued 10/27/2021 APPLICANT
CofO in Progress 4/20/2023 RAUL OLAGI
CofO Issued 4/24/2023 MICHAEL SMITH
Permit Finaled 4/24/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/3/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/3/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 9/17/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/20/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/1/2021 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/1/2021 Corrections Issued RAUL OLAGI
Special/Order Compliance 11/1/2021 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 11/10/2021 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/10/2021 Corrections Issued RAUL OLAGI
Pre-Inspection 11/10/2021 Partial Inspection JESUS RODRIGUEZ
Pre-Inspection 11/10/2021 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 11/16/2021 Not Ready for Inspection RAUL OLAGI
Pre-Inspection 11/16/2021 Partial Inspection ALAN MORELOS
Pre-Inspection 11/16/2021 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 11/29/2021 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Corrections Issued ALAN MORELOS
PLUMBING-Rough 12/21/2021 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval MARK JOHNSON
Insulation 1/7/2022 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 1/12/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval RAUL OLAGI
Green Building Rough 1/12/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval RAUL OLAGI
Special/Order Compliance 3/31/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 4/28/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Approved RAUL OLAGI
PLUMBING-Rough 4/28/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 6/27/2022 Approved ALAN MORELOS
HVAC-Rough 6/27/2022 Corrections Issued ALAN MORELOS
PLUMBING-Rough 6/27/2022 Corrections Issued ALAN MORELOS
ELECTRICAL-Rough 7/14/2022 Approved CALEB MEISTER
HVAC-Rough 7/14/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 7/14/2022 Approved CALEB MEISTER
HVAC-Rough 7/20/2022 Approved ALAN MORELOS
Drywall Nailing 8/5/2022 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 8/5/2022 Not Ready for Inspection RAUL OLAGI
Drywall Nailing 8/11/2022 Partial Approval ASHLEY THOMPSON
Insulation 8/11/2022 Approved ASHLEY THOMPSON
Drywall Nailing 8/19/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 8/19/2022 Partial Approval RAUL OLAGI
Shower Pan 8/19/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 8/25/2022 Approved RAUL OLAGI
Shower Pan 8/25/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/22/2023 Approved JUAN VALENZUELA
Final 2/22/2023 Corrections Issued JUAN VALENZUELA
Green Building Final 2/22/2023 Approved JUAN VALENZUELA
Green Building Rough 2/22/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 2/22/2023 Approved JUAN VALENZUELA
Final 4/6/2023 Corrections Issued RAUL OLAGI
Final 4/20/2023 OK to Issue CofO RAUL OLAGI
Service/Power Release 4/20/2023 Approved RAUL OLAGI