7512 N BALBOA BLVD 91406
Certificate Information: 7512 N BALBOA BLVD 91406
- Application / Permit
- 21014-20000-00413
- Plan Check / Job No.
- B21VN01066
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 27'-9" X 19'-2" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE A (N) MASTER BEDROOM, MASTER BATHROOM, AND WALK IN CLOSET, INTERIOR REMODEL THE (E) SFD TO REMODEL KITCHEN , BATHROOM , LAUNDRY , LIVING ROOM , DINING ROOM , (2) BEDROOMS, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/27/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | RARES BODEA |
| Corrections Issued | 3/12/2021 | RARES BODEA |
| Applicant returned to address corrections | 9/29/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 10/6/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 10/7/2021 | APPLICANT |
| Issued | 10/27/2021 | APPLICANT |
| CofO in Progress | 4/20/2023 | RAUL OLAGI |
| CofO Issued | 4/24/2023 | MICHAEL SMITH |
| Permit Finaled | 4/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/3/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/17/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 11/1/2021 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 11/1/2021 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 11/10/2021 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 11/10/2021 | Partial Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 11/10/2021 | Partial Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 11/16/2021 | Not Ready for Inspection | RAUL OLAGI |
| Pre-Inspection | 11/16/2021 | Partial Inspection | ALAN MORELOS |
| Pre-Inspection | 11/16/2021 | Partial Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 11/29/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 12/21/2021 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Partial Approval | MARK JOHNSON |
| Insulation | 1/7/2022 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 1/12/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | RAUL OLAGI |
| Special/Order Compliance | 3/31/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 4/28/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/28/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 6/27/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 6/27/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 6/27/2022 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 7/14/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 7/14/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 7/14/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 7/20/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 8/5/2022 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 8/5/2022 | Not Ready for Inspection | RAUL OLAGI |
| Drywall Nailing | 8/11/2022 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 8/11/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 8/19/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/19/2022 | Partial Approval | RAUL OLAGI |
| Shower Pan | 8/19/2022 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 8/25/2022 | Approved | RAUL OLAGI |
| Shower Pan | 8/25/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/22/2023 | Approved | JUAN VALENZUELA |
| Final | 2/22/2023 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 2/22/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 2/22/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 2/22/2023 | Approved | JUAN VALENZUELA |
| Final | 4/6/2023 | Corrections Issued | RAUL OLAGI |
| Final | 4/20/2023 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 4/20/2023 | Approved | RAUL OLAGI |