3926 S MICHAEL AVE 90066
Certificate Information: 3926 S MICHAEL AVE 90066
- Application / Permit
- 21014-20000-00410
- Plan Check / Job No.
- B21VN01059
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) FRONT PORCH & ADD NEW 111 SQFT ADDITION TO FRONT OF SFD AND ADD NEW 24 SQFT COVERED FRONT PORCH. REPLACE WINDOWS AND INTERIOR DOORS; ADD A EXTERIOR DOOR TO REAR OF BUILDING.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | PETER MOSESIAN |
| Corrections Issued | 2/22/2021 | PETER MOSESIAN |
| Quality Review Completed | 3/11/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| Applicant returned to address corrections | 4/6/2021 | PETER MOSESIAN |
| Plan Check Approved | 9/10/2021 | PETER MOSESIAN |
| Issued | 9/22/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 8/20/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/20/2021 | NIKTA MOUSAVI |
Contact Information
| Contractor | Builderzz Inc; Lic. No.: 985199-B | 17412 VENTURA BLVD #211 ENCINO, CA 91316 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/30/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/30/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/30/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/30/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 10/28/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/28/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/28/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/29/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/29/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/29/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 11/2/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/5/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/5/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | JESUS RODRIGUEZ |
| Final | 5/6/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 5/6/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/6/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 5/6/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 5/18/2022 | Not Ready for Inspection | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | PATRICK QUALEY |
| Smoke Detectors | 5/18/2022 | Approved | PATRICK QUALEY |
| Final | 8/22/2022 | Conditional Approval | JESUS RODRIGUEZ |