3924-3926 S MICHAEL AVE 90066

Certificate Information: 3924-3926 S MICHAEL AVE 90066

Application / Permit
21014-20000-00409
Plan Check / Job No.
B21VN01059
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO ADU WITH 470 SQFT 2ND STORY ADDITION, TOTAL 885 SQFT - PER LAMC 12.22 A.33 (c) (d)
Permit Issued
Issued on 9/22/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 PETER MOSESIAN
Corrections Issued 2/22/2021 PETER MOSESIAN
Quality Review Completed 3/11/2021 OMID HEDAYAT
Building Plans Picked Up 3/11/2021 APPLICANT
Applicant returned to address corrections 4/6/2021 PETER MOSESIAN
Plan Check Approved 9/10/2021 PETER MOSESIAN
Issued 9/22/2021 APPLICANT
CofO in Progress 8/23/2022 JESUS RODRIGUEZ
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/30/2021 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 3/30/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 3/30/2021 NIKTA MOUSAVI
Specific Plan Cleared 4/9/2021 PEDRO AYALA
Hydrant and Access approval Cleared 5/19/2021 KURT CORRAL
Low Impact Development Cleared 8/20/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/20/2021 NIKTA MOUSAVI

Contact Information

Contractor Builderzz Inc; Lic. No.: 985199-B 17412 VENTURA BLVD #211      ENCINO, CA 91316
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2021 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 9/30/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 9/30/2021 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 9/30/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 11/5/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/5/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/1/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 3/1/2022 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 3/1/2022 Approved ENRIQUE MIRELES
HVAC-Rough 3/1/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 3/1/2022 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 3/22/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 3/22/2022 Corrections Issued PATRICK QUALEY
HVAC-Rough 3/22/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 3/22/2022 Corrections Issued PATRICK QUALEY
BUILDING-Rough-Frame 4/11/2022 Partial Approval PATRICK QUALEY
ELECTRICAL-Rough 4/11/2022 Approved PATRICK QUALEY
PLUMBING-Rough 4/11/2022 Approved PATRICK QUALEY
Underground Mechanical 4/11/2022 Partial Approval PATRICK QUALEY
BUILDING-Rough-Frame 4/18/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 4/18/2022 Approved PATRICK QUALEY
Shower Pan 4/18/2022 Approved PATRICK QUALEY
Insulation 4/21/2022 Approved PATRICK QUALEY
Drywall Nailing 5/3/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 5/3/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 6/22/2022 Approved JESUS RODRIGUEZ
Final 6/22/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/22/2022 Approved JESUS RODRIGUEZ
HVAC-Final 6/22/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/22/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 6/22/2022 Approved JESUS RODRIGUEZ
Final 7/7/2022 Corrections Issued PATRICK QUALEY
Final 8/4/2022 Not Ready for Inspection JESUS RODRIGUEZ
Service/Power Release 8/4/2022 Approved JESUS RODRIGUEZ
Final 8/22/2022 OK to Issue CofO JESUS RODRIGUEZ