20260 W HALSTED ST 91311
Certificate Information: 20260 W HALSTED ST 91311
- Application / Permit
- 21014-20000-00383
- Plan Check / Job No.
- B21VN01030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 21' X 21' (E) DETACHED GARAGE AND ADD 9'-9" X 21' & 5'-9" X 10' TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ADD 5'-9" X 11' POOL BATHROOM (EXTERIOR ACCESS ONLY) & LAUNDRY ROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/15/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 3/20/2021 | RAPHAEL ROSAS |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | JEFFREY PARD |
| Permit Finaled | 6/28/2022 | JOHN JANSON |
| CofO Issued | 6/28/2022 | JOHN JANSON |
| Permit Finaled | 6/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/3/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 3/20/2021 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2021 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 9/3/2021 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 11/8/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 11/8/2021 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 11/8/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 11/8/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 11/15/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 11/29/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 12/3/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 12/3/2021 | Not Ready for Inspection | JEFFREY PARD |
| Insulation | 12/13/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/13/2021 | Approved | JAVIER RAMOS JR |
| Shower Pan | 12/15/2021 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 1/6/2022 | Approved | MORRIS JACKSON |
| Gas Test | 2/1/2022 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 2/1/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/1/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | JEFFREY PARD |
| Final | 5/9/2022 | OK to Issue CofO | JEFFREY PARD |
| Footing/Foundation/Slab | 5/9/2022 | Approved | JEFFREY PARD |
| Green Building Final | 5/9/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 5/9/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 5/9/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 5/9/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 5/9/2022 | Approved | JEFFREY PARD |