16957 W KNAPP ST 91343
Certificate Information: 16957 W KNAPP ST 91343
- Application / Permit
- 21014-20000-00378
- Plan Check / Job No.
- B21VN01016
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 7' X 24' ADDITION FOR A (N) BATHROOM AND WALK IN CLOSET TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 5/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/11/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 4/6/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/7/2021 | APPLICANT |
| Issued | 12/2/2021 | APPLICANT |
| CofO in Progress | 5/3/2023 | RAUL OLAGI |
| CofO Issued | 5/7/2023 | DEROLD HAUFF |
| Permit Finaled | 5/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Watercourse | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 3/23/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Ketterling Construction; Lic. No.: 725126-B | 17601 MAYALL STREET NORTHRIDGE, CA 91325 |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 255 W 5TH ST APT 706 SAN PEDRO, CA 90731 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/13/2022 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 1/21/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 5/5/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/5/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/5/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/11/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/11/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/11/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/11/2022 | Approved | RAUL OLAGI |
| Insulation | 5/20/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 5/26/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/10/2022 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 6/10/2022 | Approved | DEANDRE HOFFMAN |
| Final | 3/10/2023 | No Access for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 3/10/2023 | No Access for Inspection | RAUL OLAGI |
| Final | 5/3/2023 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/3/2023 | Approved | RAUL OLAGI |