16957 W KNAPP ST 91343

Certificate Information: 16957 W KNAPP ST 91343

Application / Permit
21014-20000-00378
Plan Check / Job No.
B21VN01016
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 7' X 24' ADDITION FOR A (N) BATHROOM AND WALK IN CLOSET TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 5/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 RAPHAEL ROSAS
Corrections Issued 2/11/2021 RAPHAEL ROSAS
Plan Check Approved 4/6/2021 RAPHAEL ROSAS
Building Plans Picked Up 4/7/2021 APPLICANT
Issued 12/2/2021 APPLICANT
CofO in Progress 5/3/2023 RAUL OLAGI
CofO Issued 5/7/2023 DEROLD HAUFF
Permit Finaled 5/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/2/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 3/2/2021 ADRIAN CASTRO
Watercourse Cleared 3/2/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 3/23/2021 PATRICK MISCHLICH

Contact Information

Contractor Ketterling Construction; Lic. No.: 725126-B 17601 MAYALL STREET      NORTHRIDGE, CA 91325
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2022 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 1/21/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/5/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/5/2022 Approved RAUL OLAGI
PLUMBING-Rough 5/5/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/11/2022 Approved RAUL OLAGI
Green Building Rough 5/11/2022 Approved RAUL OLAGI
HVAC-Rough 5/11/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/11/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 5/11/2022 Approved RAUL OLAGI
Insulation 5/20/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 5/26/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 6/10/2022 Approved DEANDRE HOFFMAN
Shower Pan 6/10/2022 Approved DEANDRE HOFFMAN
Final 3/10/2023 No Access for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 3/10/2023 No Access for Inspection RAUL OLAGI
Final 5/3/2023 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/3/2023 Approved RAUL OLAGI