8607-8609 N RUBIO AVE 91343
Certificate Information: 8607-8609 N RUBIO AVE 91343
- Application / Permit
- 21014-20000-00376
- Plan Check / Job No.
- B21VN01011
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 31' 6" X 22' IRR.-SHAPE REAR PORTION OF SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT AND ADD 21' 6" X 27' BEDROOM/BATHROOM/CLOSET TO REAR OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 11/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 2/15/2021 | GURUNATH NESARAJAH |
| Plans on Hold | 11/19/2021 | GURUNATH NESARAJAH |
| Hold Released | 11/24/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 11/24/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/7/2021 | GURUNATH NESARAJAH |
| Issued | 12/7/2021 | APPLICANT |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| CofO in Progress | 11/9/2022 | RAUL OLAGI |
| CofO Issued | 11/17/2022 | MICHAEL SMITH |
| Permit Finaled | 11/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
| Miscellaneous | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
| Watercourse | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 9/20/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/20/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/20/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/21/2021 | Partial Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/6/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 1/24/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 1/28/2022 | Partial Approval | DEANDRE HOFFMAN |
| HVAC-Rough | 1/28/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 1/28/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 2/2/2022 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 2/2/2022 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 2/2/2022 | Partial Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 2/8/2022 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 2/8/2022 | Partial Approval | ALAN MORELOS |
| Shower Pan | 2/8/2022 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 2/11/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 2/11/2022 | Approved | ALAN MORELOS |
| Shower Pan | 2/11/2022 | Approved | ALAN MORELOS |
| Pre-Inspection | 3/8/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/17/2022 | Corrections Issued | RAUL OLAGI |
| Sewer | 3/17/2022 | Approved | RAUL OLAGI |
| Special/Order Compliance | 3/17/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/22/2022 | Approved | RAUL OLAGI |
| Final | 8/22/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 8/22/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 8/22/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 8/22/2022 | Approved | RAUL OLAGI |
| Final | 11/9/2022 | OK to Issue CofO | RAUL OLAGI |