4968 N NOELINE AVE 91436

Certificate Information: 4968 N NOELINE AVE 91436

Application / Permit
21014-20000-00374
Plan Check / Job No.
B21VN01004
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 22'-6" X 26'-8" IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/17/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 RAPHAEL ROSAS
Corrections Issued 2/13/2021 RAPHAEL ROSAS
Applicant returned to address corrections 5/7/2021 RAPHAEL ROSAS
Issued 5/17/2021 APPLICANT
Building Plans Picked Up 5/18/2021 APPLICANT
CofO in Progress 3/16/2022 ROBERT GOLD
Permit Finaled 3/16/2022 JOHN JANSON
CofO Issued 3/16/2022 JOHN JANSON
Permit Finaled 3/16/2022 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 3/11/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/30/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 5/2/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/3/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/9/2021 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/11/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 6/23/2021 Partial Approval VINCENT HANLEY
Green Building Rough 6/23/2021 Not Ready for Inspection VINCENT HANLEY
Insulation 6/23/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/28/2021 Partial Approval RONALD COWAN
ELECTRICAL-Rough 7/28/2021 Approved RONALD COWAN
Green Building Rough 7/28/2021 Corrections Issued RONALD COWAN
PLUMBING-Rough 7/28/2021 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 8/2/2021 Approved RONALD COWAN
PLUMBING-Rough 8/2/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 8/4/2021 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2021 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 8/4/2021 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Approved DAVID SANDOVAL
Green Building Rough 8/6/2021 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 8/11/2021 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 8/13/2021 Partial Approval RONALD COWAN
Insulation 8/13/2021 Approved RONALD COWAN
Interior/Exterior Lathing 8/13/2021 Partial Approval RONALD COWAN
Drywall Nailing 8/18/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 8/18/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 11/29/2021 Approved ROBERT GOLD
Final 11/29/2021 Partial Inspection ROBERT GOLD
Green Building Final 11/29/2021 Approved ROBERT GOLD
Green Building Rough 11/29/2021 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Approved ROBERT GOLD
Smoke Detectors 11/29/2021 Approved ROBERT GOLD
Final 3/16/2022 OK to Issue CofO ROBERT GOLD