4968 N NOELINE AVE 91436
Certificate Information: 4968 N NOELINE AVE 91436
- Application / Permit
- 21014-20000-00374
- Plan Check / Job No.
- B21VN01004
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 22'-6" X 26'-8" IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/17/2021
- Issuing Office
- Current Status
- CofO Issued on 3/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/13/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/7/2021 | RAPHAEL ROSAS |
| Issued | 5/17/2021 | APPLICANT |
| Building Plans Picked Up | 5/18/2021 | APPLICANT |
| CofO in Progress | 3/16/2022 | ROBERT GOLD |
| Permit Finaled | 3/16/2022 | JOHN JANSON |
| CofO Issued | 3/16/2022 | JOHN JANSON |
| Permit Finaled | 3/16/2022 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/11/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 5/2/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/9/2021 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/11/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 6/23/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 6/23/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/28/2021 | Partial Approval | RONALD COWAN |
| ELECTRICAL-Rough | 7/28/2021 | Approved | RONALD COWAN |
| Green Building Rough | 7/28/2021 | Corrections Issued | RONALD COWAN |
| PLUMBING-Rough | 7/28/2021 | Corrections Issued | RONALD COWAN |
| ELECTRICAL-Rough | 8/2/2021 | Approved | RONALD COWAN |
| PLUMBING-Rough | 8/2/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 8/4/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 8/4/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/6/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/11/2021 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/13/2021 | Partial Approval | RONALD COWAN |
| Insulation | 8/13/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 8/13/2021 | Partial Approval | RONALD COWAN |
| Drywall Nailing | 8/18/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 8/18/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | ROBERT GOLD |
| Final | 11/29/2021 | Partial Inspection | ROBERT GOLD |
| Green Building Final | 11/29/2021 | Approved | ROBERT GOLD |
| Green Building Rough | 11/29/2021 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/29/2021 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 11/29/2021 | Approved | ROBERT GOLD |
| Final | 3/16/2022 | OK to Issue CofO | ROBERT GOLD |