15123 W VALERIO ST 91405
Certificate Information: 15123 W VALERIO ST 91405
- Application / Permit
- 21014-20000-00371
- Plan Check / Job No.
- B21VN00994
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-5" X 17' GROUND FLOOR ADDITION AND 35' X 17' SECOND STORY ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (1154 SQ FT) PER LAMC 12.22 A. 33(c) and (d)
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- Issued on 6/9/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 2/20/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/7/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/24/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| Issued | 6/9/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/27/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/4/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/16/2021 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 1/31/2022 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 8/8/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/8/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/26/2022 | Partial Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 11/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 1/24/2023 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 1/26/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/2/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 2/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/2/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 2/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/21/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 3/6/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/12/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/18/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/29/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 4/29/2025 | Approved | VINCENT HANLEY |