5324 N AMIGO AVE 91356
Certificate Information: 5324 N AMIGO AVE 91356
- Application / Permit
- 21014-20000-00358
- Plan Check / Job No.
- B21VN00946
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8' X 22' 6" ADDITION TO REAR, 9' X 22' 6" OPEN TRELLIS ADDITION, REMOVE (E) REAR PATIO COVER AND REFRAME PORTION OF (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 2/15/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 1/14/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 1/29/2022 | SERGIO MUNIZ |
| Plan Check Approved | 2/11/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Issued | 2/25/2022 | APPLICANT |
| CofO in Progress | 4/22/2025 | JOHN KIDWELL |
| CofO Issued | 4/28/2025 | JOHN JANSON |
| Permit Finaled | 4/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 1/3/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/4/2022 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 1/30/2022 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 1/30/2022 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Ecs Builders Group Inc; Lic. No.: 1035916-B | 12038 TIARA ST VALLEY VILLAGE, CA 91607 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/9/2022 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/20/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 5/20/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 5/20/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 5/27/2022 | Approved | MORRIS JACKSON |
| Insulation | 6/1/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/10/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/10/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 10/28/2022 | Approved | DAVID SANDOVAL |
| HVAC-Final | 10/28/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 10/28/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/27/2025 | Corrections Issued | JOHN KIDWELL |
| Final | 3/27/2025 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/27/2025 | Approved | JOHN KIDWELL |
| Green Building Final | 3/27/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 3/27/2025 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 3/27/2025 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/8/2025 | Approved | JOHN KIDWELL |
| Final | 4/8/2025 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 4/8/2025 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Approved | JOHN KIDWELL |