4221 W 60TH ST 90043
Certificate Information: 4221 W 60TH ST 90043
- Application / Permit
- 21014-20000-00311
- Plan Check / Job No.
- B21VN00829
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-3" X 19'-10" DETACHED GARAGE AND ADD 2'-5" X 16'-10" FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | JENNIFER LEE |
| Corrections Issued | 2/17/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 3/22/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 4/7/2021 | JENNIFER LEE |
| Plan Check Approved | 4/19/2021 | JENNIFER LEE |
| Issued | 4/19/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 11/18/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
| CofO Issued | 11/19/2025 | DEROLD HAUFF |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/2/2021 | PATRICK MISCHLICH |
| Address approval | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 3/4/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 3/11/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/26/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/26/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/26/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/16/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 11/16/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 11/16/2021 | No Access for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/1/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/12/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 4/12/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/15/2022 | Approved | HORACE FULTZ |
| Insulation | 6/10/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/15/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/15/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/8/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/14/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/14/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/4/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 8/4/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Final | 8/4/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Final | 8/4/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 8/13/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Final | 10/30/2025 | Approved | SALVADOR MARTINEZ |
| Final | 10/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 10/30/2025 | Conditional Approval | SALVADOR MARTINEZ |
| PLUMBING-Final | 10/30/2025 | Approved | SALVADOR MARTINEZ |
| Final | 11/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 11/17/2025 | OK to Issue CofO | SALVADOR MARTINEZ |