14320 W HAYNES ST 91401
Certificate Information: 14320 W HAYNES ST 91401
- Application / Permit
- 21014-20000-00309
- Plan Check / Job No.
- B21VN00825
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' (E) REC ROOM AND ADD 15' X 16' TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). REMODEL (E) ATTACHED CARPORT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/12/2022
- Issuing Office
- Current Status
- CofO Issued on 10/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/14/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Issued | 3/12/2022 | APPLICANT |
| CofO in Progress | 9/20/2024 | RYAN SALAZAR |
| Permit Finaled | 10/3/2024 | DANIEL ORRANTE |
| CofO Issued | 10/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/8/2021 | CARLOS AGUILERA |
| HPOZ | Cleared | 12/30/2021 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 12/30/2021 | SUKI GERSHENHORN |
| ZI | Cleared | 12/30/2021 | SUKI GERSHENHORN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mena,, Rolando A; Lic. No.: C50331 | 544 1/2 BRITTANIA ST #A LOS ANGELES, CA 90033 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/26/2024 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | RYAN SALAZAR |
| Final | 8/13/2024 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/13/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 8/13/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/13/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 8/13/2024 | Approved | RYAN SALAZAR |
| Final | 9/20/2024 | OK to Issue CofO | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | No Access for Inspection | RYAN SALAZAR |
| Service/Power Release | 9/20/2024 | Approved | RYAN SALAZAR |