521 N FORMOSA AVE 90036

Certificate Information: 521 N FORMOSA AVE 90036

Application / Permit
21014-20000-00302
Plan Check / Job No.
B21VN00806
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
27'-5" X 28'-5" ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH INTERIOR REMODEL
Permit Issued
Issued on 8/17/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 SELLA BENYAMIN
Corrections Issued 2/17/2021 SELLA BENYAMIN
Quality Review Completed 2/19/2021 STEVEN KIM
Building Plans Picked Up 2/25/2021 APPLICANT
Issued 8/17/2021 APPLICANT
Plan Check Approved 8/18/2021 SELLA BENYAMIN
CofO in Progress 3/11/2022 CHRIS CHRISTENSEN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 4/26/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/27/2021 WALLIE JONG
Low Impact Development Cleared 7/30/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/3/2021 WALLIE JONG

Contact Information

Contractor L E Construction & Development Inc; Lic. No.: 1051866-B 7111 SANTA MONICA BLVD   SUITE B-272    LOS ANGELES, CA 90046
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Final 8/20/2021 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/24/2021 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 8/24/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/24/2021 Approved CHRIS CHRISTENSEN
Final 8/24/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/24/2021 Conditional Approval CHRIS CHRISTENSEN
Green Building Final 8/24/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 8/24/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 8/24/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 8/24/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 8/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Final 8/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 8/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Subgrade 8/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 8/24/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/24/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 8/24/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 8/27/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/2/2021 Approved CHRIS CHRISTENSEN
Final 9/2/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/2/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 9/2/2021 Approved CHRIS CHRISTENSEN
METHANE-Final 9/2/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 9/2/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 9/2/2021 Approved CHRIS CHRISTENSEN
Pool Piping 9/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Gunite 9/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Pool Piping 9/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Gunite 9/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Final 12/27/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Final 1/19/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 2/18/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 3/10/2022 OK to Issue CofO CHRIS CHRISTENSEN