521 N FORMOSA AVE 90036
Certificate Information: 521 N FORMOSA AVE 90036
- Application / Permit
- 21014-20000-00302
- Plan Check / Job No.
- B21VN00806
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 27'-5" X 28'-5" ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH INTERIOR REMODEL
- Permit Issued
- Issued on 8/17/2021
- Issuing Office
- Current Status
- CofO Issued on 4/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | SELLA BENYAMIN |
| Corrections Issued | 2/17/2021 | SELLA BENYAMIN |
| Quality Review Completed | 2/19/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Issued | 8/17/2021 | APPLICANT |
| Plan Check Approved | 8/18/2021 | SELLA BENYAMIN |
| CofO in Progress | 3/11/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
| CofO Issued | 4/1/2022 | DEROLD HAUFF |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/26/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 7/30/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | WALLIE JONG |
Contact Information
| Contractor | L E Construction & Development Inc; Lic. No.: 1051866-B | 7111 SANTA MONICA BLVD SUITE B-272 LOS ANGELES, CA 90046 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Final | 8/20/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/24/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/24/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 8/24/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/24/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Final | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 8/24/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Final | 8/24/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 8/24/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 8/24/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/24/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/27/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 9/2/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Final | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 9/2/2021 | Approved | CHRIS CHRISTENSEN |
| Pool Piping | 9/2/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Gunite | 9/2/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pool Piping | 9/20/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Gunite | 9/20/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 12/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 1/19/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 2/18/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/10/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |