923 N LAUREL AVE 90046
Certificate Information: 923 N LAUREL AVE 90046
- Application / Permit
- 21014-20000-00278
- Plan Check / Job No.
- B21VN00739
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 2ND STORY ADDITION FOR A RECREATION ROOM OVER THE (E) DETACHED GARAGE.
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | COLIN LOREDO |
| Corrections Issued | 2/16/2021 | COLIN LOREDO |
| Quality Review Completed | 3/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Plan Check Approved | 4/12/2021 | COLIN LOREDO |
| Issued | 4/15/2021 | APPLICANT |
| CofO in Progress | 7/5/2022 | ADAM ESCOTO |
| CofO Issued | 8/3/2022 | DEROLD HAUFF |
| Permit Finaled | 8/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 4/6/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/6/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/22/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/2/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/10/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 12/1/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 12/2/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 12/22/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 3/23/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/23/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/23/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/23/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/7/2022 | Approved | ADAM ESCOTO |
| Drywall Nailing | 5/2/2022 | Conditional Approval | ADAM ESCOTO |
| Green Building Rough | 5/2/2022 | Approved | ADAM ESCOTO |
| Insulation | 5/2/2022 | Corrections Issued | ADAM ESCOTO |
| Interior/Exterior Lathing | 5/2/2022 | Partial Approval | ADAM ESCOTO |
| Drywall Nailing | 7/5/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 7/5/2022 | Approved | ADAM ESCOTO |
| Final | 7/5/2022 | OK to Issue CofO | ADAM ESCOTO |
| Green Building Final | 7/5/2022 | Approved | ADAM ESCOTO |
| HVAC-Final | 7/5/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 7/5/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Required | ADAM ESCOTO |
| Smoke Detectors | 7/5/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | ADAM ESCOTO |