1738 S HAYWORTH AVE 90035

Certificate Information: 1738 S HAYWORTH AVE 90035

Application / Permit
21014-20000-00246
Plan Check / Job No.
B21VN00679
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
19'-6" X 32'-5" IRREGULAR SHAPED ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT AND WORKSHOP PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 4/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 ARTIN ZARUKIAN
Corrections Issued 2/6/2021 ARTIN ZARUKIAN
Applicant returned to address corrections 8/7/2021 ARTIN ZARUKIAN
Plan Check Approved 8/13/2021 ARTIN ZARUKIAN
Issued 8/13/2021 APPLICANT
Building Plans Picked Up 8/16/2021 APPLICANT
CofO in Progress 3/30/2023 JOSE AVILA
Permit Finaled 4/2/2023 DEROLD HAUFF
CofO Issued 4/2/2023 DEROLD HAUFF
Permit Finaled 4/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/18/2021 JUAN ASHTON
Address approval Cleared 2/23/2021 JUAN ASHTON
Low Impact Development Cleared 7/21/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 7/30/2021 DINAH GARIN
Sewer availability Cleared 8/3/2021 DINAH GARIN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Superior Home Builders Inc; Lic. No.: 875933-B 6569 CLEOMOORE AVE      WEST HILLS, CA 91307

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/17/2021 Approved JOSE AVILA
PLUMBING-Rough 11/22/2021 Partial Approval JOSE AVILA
Footing/Foundation/Slab 11/30/2021 Approved JOSE AVILA
METHANE-Barrier 11/30/2021 Approved JOSE AVILA
METHANE-Subgrade 11/30/2021 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 12/23/2021 Partial Approval JOSE AVILA
ELECTRICAL-Rough 12/23/2021 Approved JOSE AVILA
Green Building Rough 12/23/2021 Partial Approval JOSE AVILA
HVAC-Rough 12/23/2021 Corrections Issued JOSE AVILA
METHANE-Rough 12/23/2021 Approved JOSE AVILA
PLUMBING-Rough 12/23/2021 Approved JOSE AVILA
Rough-Elec/Plmb/HVAC 12/23/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 1/3/2022 Approved JOSE AVILA
Green Building Rough 1/3/2022 Approved JOSE AVILA
HVAC-Rough 1/3/2022 Approved JOSE AVILA
Insulation 1/3/2022 Approved JOSE AVILA
Interior/Exterior Lathing 1/6/2022 Not Ready for Inspection JOSE AVILA
Shower Pan 1/6/2022 Approved JOSE AVILA
Underground Mechanical 1/6/2022 Approved JOSE AVILA
Drywall Nailing 2/7/2022 Approved JOSE AVILA
Interior/Exterior Lathing 2/7/2022 Approved JOSE AVILA
Interior/Exterior Lathing 3/2/2022 Approved AMY COLIN
Final 5/2/2022 Corrections Issued JOSE AVILA
Green Building Final 5/2/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 5/2/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 6/2/2022 Approved JOSE AVILA
Final 6/2/2022 Corrections Issued JOSE AVILA
Green Building Final 6/2/2022 Approved JOSE AVILA
HVAC-Final 6/2/2022 Approved JOSE AVILA
PLUMBING-Final 6/2/2022 Approved JOSE AVILA
Smoke Detectors 6/2/2022 Approved JOSE AVILA
Final 3/29/2023 OK to Issue CofO JOSE AVILA