12832 W HALKIRK ST 91604

Certificate Information: 12832 W HALKIRK ST 91604

Application / Permit
21014-20000-00218
Plan Check / Job No.
B21VN00606
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO ALL INTERIOR WALLS & PORTIONS OF CEILING W/ (E) ROOF & EXTERIOR WALLS TO REMAIN; ADD (N) COV'D PATIO AT REAR (IRR 39'-6" X 10'-9"; ADD (N) FRONT PORCH ( 5'-3" X 10'-5")
Permit Issued
Issued on 3/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 NILOOFAR MEHRAIN
Corrections Issued 2/9/2021 NILOOFAR MEHRAIN
Quality Review Completed 2/16/2021 CHON CHIO KUO
Building Plans Picked Up 2/17/2021 APPLICANT
Applicant returned to address corrections 1/19/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/12/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/23/2022 NILOOFAR MEHRAIN
Plan Check Approved 10/7/2022 NILOOFAR MEHRAIN
Issued 3/7/2023 APPLICANT
CofO in Progress 9/10/2025 CHRISTOPHE COCHRAN
Permit Finaled 10/8/2025 RUBEN SALAS
CofO Issued 10/8/2025 RUBEN SALAS
Permit Finaled 10/8/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/15/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/15/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/15/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/15/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Permit Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Street Frontage Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 4/24/2021 KURT CORRAL
Trees in Parkway Cleared 7/1/2021 JOHN KIM
Low Impact Development Cleared 11/9/2021 LONDY ALVARADO
GPI Written Notices Cleared 1/19/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/19/2022 NILOOFAR MEHRAIN
Roof/Waste drainage to street Cleared 11/9/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/26/2023 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/18/2023 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 8/23/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/28/2023 Approved CHRISTOPHE COCHRAN
Special/Order Compliance 10/2/2023 No Access for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/4/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 12/4/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/4/2023 Corrections Issued CHRISTOPHE COCHRAN
Sewer 12/4/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/7/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 2/7/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/12/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/18/2024 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 3/18/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/18/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Wood Construction 3/19/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/1/2024 Conditional Approval JOHN COLEMAN
Interior/Exterior Lathing 4/1/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 4/1/2024 No Access for Inspection JOHN COLEMAN
Insulation 4/10/2024 Conditional Approval CHRISTOPHE COCHRAN
Drywall Nailing 4/30/2024 Approved CHRISTOPHE COCHRAN
Insulation 4/30/2024 No Access for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/5/2024 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 6/13/2024 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 6/24/2024 Corrections Issued CHRISTOPHE COCHRAN
Shower Pan 7/9/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/21/2025 Approved CHRISTOPHE COCHRAN
Final 8/21/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 8/21/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 8/21/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/21/2025 Approved CHRISTOPHE COCHRAN
Final 9/5/2025 Corrections Issued MISAEL ESPARZA
Final 9/10/2025 OK to Issue CofO CHRISTOPHE COCHRAN