20100 W PICCADILLY LANE 91326
Certificate Information: 20100 W PICCADILLY LANE 91326
- Application / Permit
- 21014-20000-00213
- Plan Check / Job No.
- B21VN00594
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 18' X 34' LATTICE ROOF PATIO COVER ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 7/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/9/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/21/2021 | RAPHAEL ROSAS |
| Issued | 5/7/2021 | APPLICANT |
| Building Plans Picked Up | 5/12/2021 | APPLICANT |
| CofO in Progress | 7/23/2021 | DAVID SCANTLIN |
| Permit Finaled | 7/26/2021 | JOHN JANSON |
| CofO Issued | 7/26/2021 | JOHN JANSON |
| Permit Finaled | 7/26/2021 | JOHN JANSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/16/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/16/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/16/2021 | MIGUEL GAMBOA |
| "T" removal | Cleared | 2/17/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 2/17/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 2/17/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 2/17/2021 | DANG NGUYEN |
| GPI Written Notices | Cleared | 5/7/2021 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 5/7/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Green Scene The; Lic. No.: 340258-B | 21220 DEVONSHIRE ST STE 102 CHATSWORTH, CA 91311 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/21/2021 | Approved | DAVID SCANTLIN |
| METHANE-Barrier | 5/21/2021 | Approved | DAVID SCANTLIN |
| METHANE-Subgrade | 5/21/2021 | Approved | DAVID SCANTLIN |
| Final | 7/12/2021 | Corrections Issued | DAVID SCANTLIN |
| METHANE-Final | 7/12/2021 | Approved | DAVID SCANTLIN |
| METHANE-Rough | 7/12/2021 | Approved | DAVID SCANTLIN |
| Reinforced Masonry Frame | 7/12/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 7/12/2021 | Approved | DAVID SCANTLIN |
| Wood Frame | 7/12/2021 | Approved | DAVID SCANTLIN |
| Final | 7/22/2021 | OK to Issue CofO | DAVID SCANTLIN |