2050 S BEVERLY DR 90034

Certificate Information: 2050 S BEVERLY DR 90034

Application / Permit
21014-20000-00210
Plan Check / Job No.
B21VN00582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 10'-1" X 23'-4" STEEL FRAMED TRELLIS WITH CABLES TO AN (E) 2-STORY SFD PER ENGINEERING.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 PARISA ZAHABI
Corrections Issued 2/3/2021 PARISA ZAHABI
Applicant returned to address corrections 3/18/2021 JENNIFER LEE
Applicant returned to address corrections 4/9/2021 PARISA ZAHABI
Issued 4/28/2021 APPLICANT
Building Plans Picked Up 5/3/2021 APPLICANT
CofO in Progress 11/7/2023 MICHAEL PELHAM
Permit Finaled 11/8/2023 DANIEL ORRANTE
CofO Issued 11/8/2023 DANIEL ORRANTE
Permit Finaled 11/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/4/2021 PATRICK MISCHLICH

Contact Information

Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2021 Approved EVAN COOPER
METHANE-Barrier 6/24/2021 Approved EVAN COOPER
METHANE-Subgrade 6/24/2021 Approved EVAN COOPER
Final 8/4/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Final 8/4/2021 Approved KEVIN SARGSYAN
METHANE-Rough 8/4/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Structural Steel Frame 8/4/2021 Approved KEVIN SARGSYAN
Grading Pre-Inspection 8/5/2021 No Access for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 11/2/2021 Approved EVAN COOPER
Insulation 11/6/2023 Approved MEL KHACHATOURIAN
Final 11/7/2023 OK to Issue CofO MICHAEL PELHAM